Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

September 2023

THESSALONIKI_09_2023-1024x411
  • NEW RAILWAY Station: Completed are the works for the installation of granite covers at the transfer level, as well as the installation of perforated soundproof panels at the level of tracks 1 and 2. In progress are works related to the reinstatement of the surrounding area of the forestation (backfilling, road paving, slab paving), works related to the construction of the west shaft, the installation of the lighting system, as well as works for the electrical connections of lifts.
  • DIMOKRATIAS Station: Completed are works for the installation of perforated soundproof panels at the level of tracks 1 and 2 and in progress are works for the connection of the equipment of the ventilation/air conditioning system, as well as works for the installation of cables of the Building Automation Control System (BACS).
  • VENIZELOU Station: Completed are works for the layering of granite slabs at the sub-base of the platform level floor, the installation of doors as well as the construction of raised floors in the technical rooms. In progress are works for the construction of the permanent lining and undisturbed cut for the connection with the main station of the north and south access, assembly works of the escalators inside the station, works for the installation of the air ducts of the ventilation/air conditioning system, works for the installation of electrical grids and the construction of earthing in the E/M areas’ level, works for the connection of the signaling system, as well as works for the construction of piping in the pumping station. In addition, in progress are the works for placing back and preservation of the archaeological finds / units at level -1.
  • AGIAS SOFIAS Station: Completed are the steel cladding works over the PSDs, works for the construction of the shed at the north access, as well as reinstatement works in the area of Makedonomachon Square. In progress are works for the construction of false ceilings at platform level, painting works, works for the installation of the lighting system, as well as works for the installation of trays, cables and earthing.
  • SINTRIVANI Station: Completed are the works for the installation and connections of the fire rated cables with the Uninterrupted Power Supply (UPS) equipment, while in progress is the testing of all installed electromechanical systems.
  • PANEPISTIMIO Station: Completed are works for the installation and connections of the fire rated cables with the UPS equipment and in progress are reinstatement works, steel cladding works, as well as testing of all installed electromechanical systems.
  • PAPAFI Station: Completed are works for cladding the Papafio Institute fencing piers using decorative small bricks, while in progress are works for the installation of lighting fixtures in the public areas, as well as testing of all installed electromechanical systems.
  • EFKLIDIS Station: In progress are works for the installation of lighting fixtures, as well as testing of all installed electromechanical systems.
  • FLEMING Station: Completed are steel cladding works in the public areas, while in progress is testing of all installed electromechanical systems.
  • ANALIPSI Station: Completed are works for the dismantling of the worksite area slab, while in progress are works for the construction of earthing, for setting and commissioning the escalators inside the station, as well as testing of all installed electromechanical systems.
  • 25 MARTIOU Station: Completed are works for the installation and connections of fire rated cables with the UPS equipment, while in progress are works for the completion of the ventilation/air conditioning system, as well as testing of all installed electromechanical systems.
  • VOULGARI Station: Completed are works for the installation and connections of shielded cables of the tunnel ventilation system equipment, as well as works for the installation of ventilation/air conditioning system equipment, while in progress is the testing of all installed electromechanical systems.
  • NEA ELVETIA Station: Completed are works for the installation and connections of the fire rated cables with the UPS equipment and in progress are works for the installation of the power distribution system cables, works for the connection of the equipment of the ventilation/air conditioning system, works for the installation and connections of the cables of the jet fans at the tunnel extending between the station and the Depot, as well as tests in all E/M systems installed.

DEPOT

  • Building Complex Ι: Completed are the works for the installation of the equipment of the access control and intrusion detection system at Complex I and at building 7.
  • Building Complex ΙΙ: In progress are indoor and outdoor painting works, as well as works for the installation of ironmongery, false ceilings and ceramic tiles. With regard to the electromechanical works, completed are works for the construction of insulation of Fan Coil units (FCU), the installation of A/C piping at the platform and in building 4, as well as works for the installation of lighting at the small structure on the roof. In progress are works for the installation of air ducts in buildings 3 and 4, the installation and construction of A/C pipes insulation, works for the installation of FCUs, cabling works of the lighting system, installation and connections of the BACS equipment. In the surrounding area, completed are the works for the installation of the fire hydrants, as well as the installation of the fuel tank.

TRACKWORK: Completed is the activation of the traction power in the entire line.

  • In progress are testing and commissioning works.
WCAG