Piraeus Project progress

November 2012

The construction of retaining piles in the TBM startup shaft has been completed and excavation works are in progress. All works related to the dismantling of various items, relocations of kiosks and transplantations have been completed in the six (6) stations of the Project and the archaeological survey, as well…
Μάθε Περισσότερα

October 2012

The pile driving works at the TBM Start-up Shaft have been completed; The relocation of the Public Utility Organizations networks is in progress at AGHIA VARVARA Station; The archaeological survey is in progress at AGHIA VARVARA, NIKEA, KORYDALLOS and DIMOTIKO THEATRO Stations; The worksite occupation related works are in progress…
Μάθε Περισσότερα

September 2012

The works for the construction of temporary retaining piles in the TBM access shaft are in progress; The archaeological survey in KORYDALLOS Station area is at an advanced stage; The worksite installation of the Contractor in MANIATIKA Station area has been completed; The works for the relocation of the kiosks…
Μάθε Περισσότερα

August 2012

The archaeological excavation in the TBM start up shaft in the area of Aghia Varvara is completed; The dismantling and transplantation works, as well as the execution of investigation trenches for PUO networks in AGHIA VARVARA, NIKEA and KORYDALLOS Stations are at an advanced stage; The work site occupation of…
Μάθε Περισσότερα

July 2012

The archaeological investigation at the Start-up Shaft of the Tunnel Boring Machine (TBM) in the area of Aghia Varvara is in progress. The worksite occupation in KORYDALLOS and NIKEA Stations is in progress. The Supplementary Boreholes Plan along the Metro Extension to Piraeus has been completed.
Μάθε Περισσότερα