Piraeus Project progress

June 2018

• Komninou Shaft: The works for the construction of a staircase is in progress. • AGHIA VARVARA Station: In progress are the preliminary activities for the commencement of the architectural works in M. Alexandou Shaft. At recess 4+867, the works for the installation of the metal structure in the TBM…
Μάθε Περισσότερα

May 2018

• Komninou Shaft: The works for the permanent lining of the shaft walls have been completed and the construction of a staircase is in progress. • AGHIA VARVARA Station: The works for the placement of ventilation trays and brackets are in progress. • M. Alexandrou shaft: The construction of the…
Μάθε Περισσότερα

February 2018

• AGHIA VARVARA Station – Doors painting works and waterproofing works are in progress. • KORYDALLOS Station – Access 2 excavation works are in progress. Pissidias shaft: Excavation works and works for the installation of the temporary retaining system, foundation improvement and temporary retaining works have been completed. Excavation works…
Μάθε Περισσότερα

January 2018

• TBM access shaft: The works for the construction and waterproofing of perimeter walls has been completed. • AGHIA VARVARA Station – M. Alexandrou shaft: The works for the permanent lining of the shaft’s wall are in progress. • KORYDALLOS Station – Pissidias shaft: Excavation and temporary retaining works (levels…
Μάθε Περισσότερα

April 2017

• Along the double track tunnel, from the beginning of the extension up to TBM startup shaft, the permanent lining of the tunnel invert has been completed, while the works for the permanent lining of the tunnel vault are in progress. • AGHIA VARVARA Station: Works for the construction of…
Μάθε Περισσότερα

January 2017

• Along the double track tunnel, from the beginning of the extension up to TBM startup shaft, phases B’ and C’ excavation works of to Aghia Marina have been completed. In progress are the preparatory works for the demolition of the wall for connection with the tunnel. • AGHIA VARVARA…
Μάθε Περισσότερα

December 2016

• KORYDALLOS Station: Investigation trenches for the Public Utility networks have been completed in Pissidias Shaft. • NIKEA Station: Works for the construction of a section of the station’s roof slab in the area where it is connected to the permanent lining structure of the northern entrance are in progress.…
Μάθε Περισσότερα

November 2016

At the beginning of the extension, in the double track NATM tunnel, Phase A tunnel excavation works from the TBM shaft to Aghia Marina have been completed. Phase B and C tunnel excavation works are in progress. KORYDALLOS Station: Painting works are in progress. NIKEA Station: Painting works are in…
Μάθε Περισσότερα

October 2016

NIKEA Station: The works for the construction of industrial floors at the concourse level of the Station are in progress. In addition, in progress is the construction of the permanent lining of the main station (phase B’): construction of exterior perimeter walls at the E/M level of the floor slab…
Μάθε Περισσότερα

September 2016

Komninou Shaft: The works for the worksite installations have been completed. Excavation and temporary retaining works are in progress. AGHIA VARVARA Station: Backfilling works are in progress. At Taxiarchon Shaft, the construction and concreting of the foundation slab are completed. KORYDALLOS Station: Filling works and works related to industrial and…
Μάθε Περισσότερα