Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Piraeus Project progress

August 2015

AGHIA VARVARA Station: The construction works and the works for stressing the prestressed anchors at Taxiarchon Shaft are about to be completed; KORUDALLOS Station: The works for waterproofing the station are in progress; NIKEA Station: The TBM maintenance works are in progress; PIRAEUS Station: The works for the construction of…
Μάθε Περισσότερα

July 2015

AGHIA VARVARA Station: The works for the construction of the roof slab are in progress; NIKEA Station: The TBM maintenance works and those for the construction of a portion of the main station’s roof slab are in progress; MANIATIKA Station: In progress are the works for the construction of the…
Μάθε Περισσότερα

June 2015

AGHIA VARVARA Station: The works for the construction of columns down to the concourse level have been completed, while the works for the construction of access 3 are in progress; KORYDALLOS Station: The removal of the launch cradle and the TBM false tunnel precast segments has been completed. The undisturbed…
Μάθε Περισσότερα

May 2015

AGHIA VARVARA Station: The roof slab construction works are in progress; KORYDALLOS Station: Works for the construction of Station access piles have been completed, while the partial relocation of the TBM worksite installations is in progress; NIKEA Station: The works for the concreting of columns up to the mechanical floor…
Μάθε Περισσότερα

April 2015

AGHIA VARVARA Station: The works for the construction of columns up to the ceiling level were completed, while the woks for the construction of perimeter walls up to the ceiling level and the roof slab construction works are in progress; KORYDALLOS Station: Works for the construction of Station access piles…
Μάθε Περισσότερα

March 2015

AGHIA VARVARA Station: Excavation works and works for the construction and tensioning of pre-stressed anchors in Taxiarchon Shaft are in progress; KORYDALLOS Station: Waterproofing, permanent lining reinforcement and concreting works are in progress; NIKEA Station: The works for the waterproofing for the main station foundation slab, the concreting of the…
Μάθε Περισσότερα

February 2015

AGHIA VARVARA Station: Column construction works up to the roof level are in progress; KORYDALLOS Station: Waterproofing, permanent lining reinforcement and concreting works are in progress; NIKEA Station: Column concreting works from platform level -3 to the concourse slab at level -2, as well as works for the concreting of…
Μάθε Περισσότερα

January 2015

AGHIA VARVARA Station: The works for the construction of the mechanical floor slab are in progress; KORYDALLOS Station: Concreting works of the Station foundation slab and perimeter walls up to the concourse level are in progress; NIKEA Station: In the framework of the construction of the main Station permanent lining,…
Μάθε Περισσότερα

December 2014

AGHIA VARVARA Station: The works for the construction of columns up to the mechanical floor level are in progress; KORYDALLOS Station: Concreting works of the foundation slab and the perimeter walls of the Station up to the concourse level are in progress; NIKEA Station: The works for the construction of…
Μάθε Περισσότερα

October 2014

AGHIA VARVARA Station: The works for the construction of supporting columns up to the concourse level were completed, while the works for the construction of beams and the concourse slab are in progress. Moreover, the works for the construction of piles at Taxiarchon shaft are in progress; KORYDALLOS Station: The…
Μάθε Περισσότερα
WCAG