Thessaloniki Base Project progress

July 2012

The construction of inner parapet walls at EFKLIDIS Station is in progress. The excavation works at FLEMING Station are in progress. The construction of diaphragm walls at ANALIPSI Station is in progress. The ground slab at the 2nd basement of PANEPISTIMIO Station has been completed. The construction of the roof…
Μάθε Περισσότερα

June 2012

Until the present day, seventy-four per cent (74%) of the archaeological excavations has been carried out and by the end of 2012 all excavation works are expected to be completed. During the archaeological survey, more than 10,000 finds have been revealed, especially along Egnatia Odos. At the current phase, archaeological…
Μάθε Περισσότερα

April 2012

The completion percentage of the Civil Works for THESSALONIKI METRO Project reaches 42%, while the tunneling completion percentage is over 72%. The architectural finishes works, as well as the works for the installation of the electromechanical equipment of the Project have recently commenced. The archaeological excavations at four (4) locations…
Μάθε Περισσότερα

January 2012

The works for the backfilling of the archaeological trench of the Basilica church at SINTRIVANI Station are underway, while the station excavation works are in progress. The excavation works at the western part of Thessaloniki Metro Depot have commenced, while the removal of small structures located at the northern side…
Μάθε Περισσότερα

December 2011

The Court of Auditors approved a supplementary contract concerning the execution of Metro archaeological investigation works amounting to 41.8 million EURO. It is anticipated that all legal issues that have been raised by Papafeio Management will be settled soon and that the works for the construction of PAPAFIO Station will…
Μάθε Περισσότερα

November 2011

The Civil Works have been completed by 41%. 69% of the metro tunnels have been constructed until the present day. The archaeological excavation works have been completed by 57%, while the archaeological investigation works at FLEMING Station and the branching of the Metro to Stavroupoli are anticipated to be completed…
Μάθε Περισσότερα

October 2011

The two Tunnel Boring Machines (TBMs) have currently bored a total of 10,200m of single track tunnel. The archaeological investigations have been completed at SYNTRIVANI Station and the works for the construction of the station’s northern access have commenced. The works for the repair of Kyrillos duct at the New…
Μάθε Περισσότερα