Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Thessaloniki Base Project progress

September 2011

Resuming of tunneling works by the first TBM towards ANALIPSI Station is anticipated soon, while the second TBM is approaching today FLEMING Station. The construction of the diaphragm walls in ANALIPSI Station has commenced. The construction of the Northen entrance/exist of the New Railway Station is in progress. The archaeological…
Μάθε Περισσότερα

August 2011

The preliminary works for the implementation of traffic arrangements (closing down a part of Delfon street) related to the worksite installation of ANALIPSI Station are in progress. The works for the configuration of the south access of AGHIA SOFIA Station, as well as for the reinstatement of the surrounding area,…
Μάθε Περισσότερα

July 2011

The first TBM arrived at FLEMING Station. Until the present date, civil works have been completed at a percentage of 37%. The construction of ANALIPSI Station will commence very soon, since the difficult geotechnical problems that have been encountered in the area are finally solved. The reconfiguration of the designs…
Μάθε Περισσότερα

June 2011

The first TBM continues its underground journey and has already covered a distance of 318m. past EFKLIDIS Station. The construction of the 2 underground levels of FLEMING Station has been completed, while the concreting works of the station shafts are in progress. The works for the construction of the pits…
Μάθε Περισσότερα

May 2011

The works for the cleaning and maintenance of the cutter heads and the remaining facilities pertaining to the two Tunnel Boring Machines are at a completion stage. The works for the construction of EFKLIDIS Station shafts are in progress. Jet grouting works along ANALIPSI Station have been completed.
Μάθε Περισσότερα

March 2011

By the end of March 2011, the two TBMs had constructed a total of 8,850 meters of ready tunnel (single track). The archaeological excavation in the areas of VENIZELOU, AGHIAS SOFIAS and SYNTRIVANI stations is in progress. The construction of the foundation slab at EFKLIDIS station is completed and the…
Μάθε Περισσότερα

February 2011

Until the end of February 2011 both TBMs have constructed in total 8,450 meters of a completed (single-track) tunnel. The works for the construction of a temporary metal bridge at the northern section of “Dimocratias” Station are in progress. The works for the construction of micro-piles at the foundation slab…
Μάθε Περισσότερα
WCAG