Thessaloniki Base Project progress

January 2012

The works for the backfilling of the archaeological trench of the Basilica church at SINTRIVANI Station are underway, while the station excavation works are in progress. The excavation works at the western part of Thessaloniki Metro Depot have commenced, while the removal of small structures located at the northern side…
Μάθε Περισσότερα

December 2011

The Court of Auditors approved a supplementary contract concerning the execution of Metro archaeological investigation works amounting to 41.8 million EURO. It is anticipated that all legal issues that have been raised by Papafeio Management will be settled soon and that the works for the construction of PAPAFIO Station will…
Μάθε Περισσότερα

November 2011

The Civil Works have been completed by 41%. 69% of the metro tunnels have been constructed until the present day. The archaeological excavation works have been completed by 57%, while the archaeological investigation works at FLEMING Station and the branching of the Metro to Stavroupoli are anticipated to be completed…
Μάθε Περισσότερα

October 2011

The two Tunnel Boring Machines (TBMs) have currently bored a total of 10,200m of single track tunnel. The archaeological investigations have been completed at SYNTRIVANI Station and the works for the construction of the station’s northern access have commenced. The works for the repair of Kyrillos duct at the New…
Μάθε Περισσότερα

September 2011

Resuming of tunneling works by the first TBM towards ANALIPSI Station is anticipated soon, while the second TBM is approaching today FLEMING Station. The construction of the diaphragm walls in ANALIPSI Station has commenced. The construction of the Northen entrance/exist of the New Railway Station is in progress. The archaeological…
Μάθε Περισσότερα

August 2011

The preliminary works for the implementation of traffic arrangements (closing down a part of Delfon street) related to the worksite installation of ANALIPSI Station are in progress. The works for the configuration of the south access of AGHIA SOFIA Station, as well as for the reinstatement of the surrounding area,…
Μάθε Περισσότερα

July 2011

The first TBM arrived at FLEMING Station. Until the present date, civil works have been completed at a percentage of 37%. The construction of ANALIPSI Station will commence very soon, since the difficult geotechnical problems that have been encountered in the area are finally solved. The reconfiguration of the designs…
Μάθε Περισσότερα

June 2011

The first TBM continues its underground journey and has already covered a distance of 318m. past EFKLIDIS Station. The construction of the 2 underground levels of FLEMING Station has been completed, while the concreting works of the station shafts are in progress. The works for the construction of the pits…
Μάθε Περισσότερα

May 2011

The works for the cleaning and maintenance of the cutter heads and the remaining facilities pertaining to the two Tunnel Boring Machines are at a completion stage. The works for the construction of EFKLIDIS Station shafts are in progress. Jet grouting works along ANALIPSI Station have been completed.
Μάθε Περισσότερα