Thessaloniki Base Project progress

March 2011

By the end of March 2011, the two TBMs had constructed a total of 8,850 meters of ready tunnel (single track). The archaeological excavation in the areas of VENIZELOU, AGHIAS SOFIAS and SYNTRIVANI stations is in progress. The construction of the foundation slab at EFKLIDIS station is completed and the…
Μάθε Περισσότερα

February 2011

Until the end of February 2011 both TBMs have constructed in total 8,450 meters of a completed (single-track) tunnel. The works for the construction of a temporary metal bridge at the northern section of “Dimocratias” Station are in progress. The works for the construction of micro-piles at the foundation slab…
Μάθε Περισσότερα

July 2010

The construction of the roof slab at FLEMING Station, PANEPISTIMIO Station and the NEW RAILWAY STATION is in progress. The works for the PUO network diversions in ANALIPSI and PATRIKIOU Stations are in progress, while the works for the construction of the Diaphragm Walls at ANALIPSI Station have commenced. The…