Thessaloniki Base Project progress

July 2010

The construction of the roof slab at FLEMING Station, PANEPISTIMIO Station and the NEW RAILWAY STATION is in progress. The works for the PUO network diversions in ANALIPSI and PATRIKIOU Stations are in progress, while the works for the construction of the Diaphragm Walls at ANALIPSI Station have commenced. The…
Μάθε Περισσότερα

Μarch 2010

Excavation works for the construction of the roof slab at EFKLIDIS Station are in progress. Works related to the construction of the metal bridge at VENIZELOU Station (southern section of Egnatias street) were completed. The archaeological investigation is in progress at DEMOKRATIAS Station, at NEOS SIDIRODROMIKOS STATHMOS as well as…
Μάθε Περισσότερα