Thessaloniki Base Project progress

December 2009

The second Tunnel Boring Machine (ΤΒΜ2) continues its underground trip, thus having constructed 2,485m of parallel tunnel, while at the first Tunnel Boring Machine (TBM1) works related to the maintenance of the TBM’s cutterhead are executed. Works related to construction of the metal bridge at DEMOKRATIAS Station commenced. The archaeological…
Μάθε Περισσότερα

Νovember 2009

The first TBM (TBM1) reached SINTRIVANI crossover on 10/11/09, thus having constructed 2,714m of tunnel. The second TBM (TBM2) aproaches as well, having constructed 2,,125m of parallel tunnel. Works related to the construction of piles for the metal bridge at AGHIA SOFIA Station were completed. The development of the worksite…
Μάθε Περισσότερα

Οctober 2009

The first TBM (TBM1) has constructed 2600m of tunnel and approaches SINTRIVANI Station, while the second (TBM2) has constructed 1700m. of parallel tunnel and moves towards AGHIA SOFIA Station. Works related to the construction of the roof slab at PANEPISTIMIO Station as well as at the forestation of NEOS SIDIRODROMIKOS…
Μάθε Περισσότερα

September 2009

The first TBM (TBM1) has constructed 2300m of tunnel, while the second (TBM2) has constructed 1350m. of parallel tunnel. The construction of diaphragm walls at PANEPISTIMIO and EFKLIDIS Stations is in progress, while the respective works at FLEMING Station commenced. Works related to the construction of the metal bridge at…
Μάθε Περισσότερα

July 2009

The first Tunnel Boring Machine (ΤΒΜ1) has constructed 1450m of tunnel, while the second one (ΤΒΜ2) has constructed 950m. of parallel tunnel. Works related to the construction of diaphragm walls at EFKLEIDIS Station commenced. The construction of diaphragm walls at AGHIA SOFIA Station is at a completion stage (completed at a…
Μάθε Περισσότερα

June 2009

The first Tunnel Boring Machine (ΤΒΜ1) has constructed 1040m of tunnel, while the second one (ΤΒΜ2) has constructed 375m. of parallel tunnel. The construction of diaphragm walls at AGHIA SOFIA Station is at a completion stage (completed at a percentage of 82%), while diaphragm walls at PANEPISTIMIO Station commenced. PUO network…
Μάθε Περισσότερα

Μay 2009

The first TBM (ΤΒΜ 1) has bored 800m. of tunnel, while the second one (ΤΒΜ 2) has constructed 200m. of parallel tunnel. The construction of diaphragm walls at NEO SIDIRODROMIKO STATHMO was completed, while at an advanced stage is the construction of diaphragm walls at AGHIA SOFIA Station (66%). Works…
Μάθε Περισσότερα

April 2009

The first TBM has bored 600m. of tunnel, while on April 23rd the TBM named “Yorikas” started the construction of the second parallel tunnel. The construction of diaphragm walls at Neos Sidirodromikos Stathmos (completed at a percentage of 63%) and at Aghia Sofia Station (completed at a percentage of 63%)…
Μάθε Περισσότερα