Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Thessaloniki Base Project progress

August 2008

The assembly of the Tunnel Boring Machine has commenced at NEOS SIDIRODROMIKOS STATHMOS Station. The main construction works at NEOS SIDIRODROMIKOS STATHMOS, DIMOKRATIAS, VENIZELOU, SYNTRIVANI and AGHIA SOPHIA Stations advance at a rapid pace. Until the present day, the archaeological excavation works executed for the Metro construction have covered a…
Μάθε Περισσότερα

July 2008

The construction of diaphragm walls at DEMOKRATIAS Station is at a completion stage. The construction of diaphragm walls at SYNTRIVANI Station is at an advanced stage (completed at a percentage of 71%), while the excavation works at VENIZELOS Station have recently commenced. The construction of the raft at the start-up…
Μάθε Περισσότερα

June 2008

The execution of piling works is in progress (completed at a percentage of 35%) at the entrances/exits of VENIZELOS Station, while respective works at AGHIA SOFIA Station commenced. Archaeological finds were revealed at the southeastern side of SINTRIVANI Station. The excavation of the start-up shaft of the TBM in the…
Μάθε Περισσότερα

May 2008

The construction of diaphragm walls at SINTRIVANI Station (completed at a percentage of 55%) and at DEMOKRATIAS Station (completed at a percentage of 35%) is at an advanced stage, while the installation of piles at the entrances/exits of VENIZELOS Station commenced. Worksite installation of the contracting consortium at PAPAFI Station…
Μάθε Περισσότερα

April 2008

The second Tunnel Boring Machine arrived in Thessaloniki. Diaphragm walls at VENIZELOU Station were completed and works related to the installation of the metal bridge at the street level commenced. Works related to the excavation of the forestation at NEOS SIDIRODROMIKOS STATHMOS commenced. The excavation of the start-up shaft of…
Μάθε Περισσότερα

Μarch 2008

The construction of diaphragm walls at VENIZELOS Station (completed at a percentage of 98%),at SYNTRIVANI Station (completed at a percentage of 48%) as well as at DEMOKRATIAS Station (completed at a percentage of 12%) is in progress. Works related to the diversion of the non-fire resistant pipe at AGHIA SOFIA…
Μάθε Περισσότερα

February 2008

The main construction works at VENIZELOS and SYNTRIVANI Stations are in progress. Works related to the diversion of the non-fire resistant pipe at AGHIA SOFIA Station are in progress. PUO works in the area of PANEPISTIMIO Station are in progress and the worksite occupation of EFKLEIDIS Station commenced. The excavation…
Μάθε Περισσότερα
WCAG