Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Thessaloniki Base Project progress

ΒΑΣΙΚΟ ΕΡΓΟ - ΙΑΝΟΥΑΡΙΟΣ 2021

January 2021

    DIMOKRATIAS STATION: Works related to the installation of fire fighting, sewage and water supply networks at level -2 have been executed. AGHIA SOFIA Station: Preparatory works for the construction of masonry at levels -2 and -3 are in progress. SINTRIVANI Station: The works for the installation of sub-frames…
Μάθε Περισσότερα
THESSALONIKI_12_20

December 2020

  NEW RAILWAY STATION: Works related to the construction of masonry walls and plastering related works have been executed. VENIZELOU Station: The works for the removal of the equipment and installations at the south access have been completed. AGHIA SOFIA Station: Works for the construction of parapet walls’ terminations at…
Μάθε Περισσότερα

November 2020

  DIMOKRATIAS Station: In progress are works for the installation of the air duct network at level -2. VENIZELOU Station: Diaphragm walls construction works at the southern access, as well as works related to roof slab supporting piles have been completed. AGHIA SOFIA Station: Works for the construction of parapet…
Μάθε Περισσότερα
Πρόοδος Βασικού Έργου Θεσσαλονίκης - Οκτώβριος 2020

October 2020

  VENIZELOU Station: Diaphragm walls construction works at the southern access have been completed. In progress are equipment and related facilities removal works, as well as works for the construction of temporary retaining piles at the southern access. AGHIA SOFIA Station:  Surface reinstatement works at the south section of the…
Μάθε Περισσότερα
Πρόοδος βασικού έργου Θεσσαλονίκης - Σεπτέμβριος 2020

September 2020

  NEW RAILWAY Station: Works for the installation of E/M equipment bases and works for the installation of sewage and fire fighting networks have been executed. DIMOKRATIAS Station: Works for the installation of E/M equipment bases have been executed. AGHIA SOFIA Station: Works for the construction of the permanent lining…
Μάθε Περισσότερα

June 2020

NEW RAILWAY STATION: The works for the transport and distribution of rail-tracks are in progress. DIMOKRATIAS Station: The works for the transport and distribution of rail-tracks are in progress. VENIZELOU Station: The works for cutting the walls to encase the temporary backfill, as well as the preliminary works for the…
Μάθε Περισσότερα

April 2020

NEW RAILWAY STATION: The works for the construction of the filling concrete in the area of the forestation are in progress. DIMOKRATIAS Station: The works for the installation of a sewage network are in progress. VENIZELOU Station: The works for the removal of struts and monorail installation are in progress.…
Μάθε Περισσότερα

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform. DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed…
Μάθε Περισσότερα
WCAG