Thessaloniki Base Project progress

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform. DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed…
Μάθε Περισσότερα

February 2020

NEW RAILWAY Station: In progress are the works related to the lift installation and the construction of filling concrete and sidewalk base. PAPAFI Station: The works for the installation of Platform Screen Doors (PSD) have been completed. In progress are earthing construction works. FLEMING Station: In progress are the works…
Μάθε Περισσότερα

January 2020

NEW RAILWAY Station: In progress are the works related to the automatic extinguishing system using gas and to the tunnel ventilation equipment. DIMOKRATIAS Station (Station and Crossover): In progress are the works related to the network for fire fighting and installation of fire-rated air ducts of the tunnel ventilation and…
Μάθε Περισσότερα

December 2019

NEW RAILWAY STATION: Works for the reinstatement of the indoor lift and works for the preparation of the tunnel filling concrete are in progress. DIMOKRATIAS Station (Station & Crossover): In the framework of the 30th Traffic Reinstatement Plan, works for the construction of the central island at Monastiriou Street have…
Μάθε Περισσότερα

May 2019

NEW RAILWAY Station: The works for the reinstatement of the surrounding area at street level are in progress. VENIZELOU Station: The works for the construction of the station’s roof are in progress. AGHIA SOFIA Station: The works for the construction of the slab at level -2 have been completed. In…
Μάθε Περισσότερα

DECEMBER 2018

NEW RAILWAY Station: The works for the installation of ceramic tiles continue. DIMOKRATIAS Station (Station and Crossover): The reinstatement of the southern sidewalk at Monastiriou street (at the crossover), as well as the implementation of traffic phase L’ have been completed. Floor cladding works using granite slabs are in progress.…
Μάθε Περισσότερα

NOVEMBER 2018

NEW RAILWAY Station: The works for the installation of ceramic tiles in other station levels as well are at an advanced stage. DIMOKRATIAS Station (Station and Crossover): Floor cladding works using granite slabs are in progress. VENIZELOU Station: Works for burring of archaeological finds and archaeological survey related works at…
Μάθε Περισσότερα