Thessaloniki Base Project progress

November 2016

NEOS SIDIRODROMIKOS STATHMOS Station: In progress are masonry works at level -1. Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while works for the construction of the foundation slab are in progress at the northern part. DIMOKRATIAS Station: In progress is the archaeological…
Μάθε Περισσότερα

October 2016

NEOS SIDIRODROMIKOS STATHMOS Station: In progress is the archaeological excavation at the southeast and southern shaft, as well as the installation of escalators. Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while there are still in progress at the southern part. DIMOKRATIAS Station:…
Μάθε Περισσότερα

September 2016

NEW RAILWAY Station: Excavation works at the southern access are in progress. DIMOKRATIAS Crossover: The works for the construction of the foundation micro-piles are in progress. DIMOKRATIAS Station: Traffic arrangements at Monastiriou Street have been completed. The works for the construction of the raft are in progress while archaeological excavations…
Μάθε Περισσότερα

August 2016

NEW RAILWAY Station: The works for the construction of retaining piles in the shafts and the diversion of the combined-flow network are in progress. DIMOKRATIAS Station: the excavation works are completed, while in progress are the preparatory works for the subsequent traffic phase. AGHIA SOFIA Station: The works for the…
Μάθε Περισσότερα

June 2016

Dimokratias Crossover: Works for the excavation of the final level are in progress. DIMOKRATIAS Station: Completion of the construction of slab -2. Moreover, in progress is the archaeological excavation of the final level. SINTRIVANI Station – REPORT: In progress is the temporary retaining of the northern access. PAPAFI Station: In…
Μάθε Περισσότερα

May 2016

Dimokratias Crossover: The works for the installation of struts at the final level are in progress. DIMOKRATIAS Station: Completion of excavation works at level -2 of the station. In progress is the construction of slab -2. Moreover, in progress is the archaeological excavation of the northern access, the northern ventilation…
Μάθε Περισσότερα

March 2016

Dimokratias Crossover: The works for the excavation of the final level -3 are in progress. DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress. AGHIA SOFIA Station: The works for the construction of anchors for the temporary retaining of the southern access and the general excavation…
Μάθε Περισσότερα

February 2016

Dimokratias Crossover: The works for the construction of level -2 were completed, while the preparation for the excavation of level -3 is in progress. DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress. SINTRIVANI Station: Preparatory works for the excavation of level -4 are in progress.…
Μάθε Περισσότερα

January 2016

PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls are in progress. VOULGARI Station: The works for the POY network diversions, traffic arrangements and worksite installations are in progress. NEA ELVETIA Station & Crossover: At the crossover, the construction of the foundation slab is completed, while the…
Μάθε Περισσότερα