TRAM Project progress

  • Home
  • TRAM Project progress

DECEMBER 2021

The Project concerning the Tramway Extension to Piraeus has been completed since 2019, while its commissioning had been scheduled for January 2020. However, after the unfortunate incident of the fire in a building listed for preservation on Omiridou Skylitsi Street, the tramway commissioning was suspended for safety reasons, further to…
Μάθε Περισσότερα
Πρόοδος έργου ΤΡΑΜ - Ιανουάριος 2020

JANUARY 2020

  By order of the Traffic Police, ATTIKO METRO S.A. interrupted the tramway circulation for safety reasons further to the unfortunate event of a fire that burst onto a listed building located on Omiridou Skylitsi Street on 03.01.2020 adjacent to the tramway. Further to this incident, this privately owned building…
Μάθε Περισσότερα
Πρόοδος έργου ΤΡΑΜ - Δεκέμβριος 2019

DECEMBER 2019

  The construction of the tramway has already been completed, while the relevant operational tests have been successful. The delivery of the Tramway extension to Piraeus for revenue service and use by the public has been scheduled to take place at the beginning of January 2020.
Μάθε Περισσότερα

OCTOBER 2019

Α.            Tramway – Works for eliminating the risks from materials detached from the facades of the listed building at the junction of Omirou Skylitsi and Deligiorgi Streets have been completed. The tramway vehicles trial run has commenced a new. Β.            OTHER WORKS (reference to extended work fronts) Lambraki Bridge:…
Μάθε Περισσότερα

SEPTEMBER 2019

Α.            Tramway Works for eliminating the risks from materials likely to be detached from the facades of the listed building at the junction of Omirou Skylitsi and Deligiorgi Streets have commenced and are in progress. Eventual material detachment caused the suspension of the tramway vehicles trail run on 19.07.2019…
Μάθε Περισσότερα

AUGUST 2019

Α.            Tramway Further to the completion of the works for the construction of the tramway the final tests – adjustments of the systems and devices controlling the operation of the Tramway system are still pending due to the suspension of the tramway vehicle trial runs on 19.07.2019 further to…
Μάθε Περισσότερα

JULY 2019

Α.            Tramway Further to the completion of the works for the construction of the tramway (see previous progress of works), the final tests – adjustments of the systems and devices controlling the operation of the Tramway system (for integration of the extension to Piraeus into the basic network) and…
Μάθε Περισσότερα

JUNE 2019

Α.            Tramway Further to the completion of the works for the construction of the tramway (see previous progress of works), the following works are in progress. The final tests – adjustments of the systems and devices controlling the operation of the Tramway system (for integration of the extension to…
Μάθε Περισσότερα

ΜΑΥ 2019

Α. Tramway The works for the construction of the tramway corridor (trackwork – rails – catenary) have been completed. The following works are in progress: The trial run of the Tramway system and the adjustment – checking of the systems and devices controlling the operation of the Tramway system (for…
Μάθε Περισσότερα