TRAM Project progress

May 2018

A. With regard to the TRAMWAY CORRIDOR: • At Piraeus: – The following activities are in progress, which complete the Tramway Line extension to Piraeus: the construction of the Tramway corridor at Vas. Georgiou street (from the end of Tinaneios (Tinan) garden to Akti Miaouli), at Akti Miaouli pedestrian crossing…
Μάθε Περισσότερα

February 2018

A. With regard to the TRAMWAY CORRIDOR: In the remaining areas of the entire Tramway network: • Tramway corridor works have been completed: – at N. Faliro stop (installation of turnouts and connection of the Tramway extension to Piraeus with the operating tramway network) – at Mousson Street (installation of…
Μάθε Περισσότερα

January 2018

A. With regard to the TRAMWAY CORRIDOR: • The following works have been completed: Tramway corridor (trackwork – rails, infrastructure works for multiple ducts and foundation of catenary poles) – at Ethnarhou Makariou street (from N. Faliro stop –connection with the beginning of the extension- to Papandreou bridge) – at…
Μάθε Περισσότερα

April 2017

• At Ethnarhou Makariou street, the construction of the staircase connecting Karaiskaki stop with the underground pedestrian walkway has been completed. • At Lambraki bridge, the construction of the pedestrian bridge and the widening of the sidewalk are in progress. • At Grigoriou Lambraki street, the tramway corridor from the…
Μάθε Περισσότερα

January 2017

• At Ethnarhou Makariou street, in progress is the construction of Karaiskaki stop and the staircase connecting this stop with the underground pedestrian walkway. • At Papandreou bridge and at Micras Asias Street, at the completion stage are the works for the construction of the tramway corridor (fitting of rails),…
Μάθε Περισσότερα

December 2016

• At Papandreou bridge and at Mikras Asias Street, the tramway corridor at the section extending from Papandreou bridge to Gr. Lambraki entrance (after the U-turn) has been completed and tracks are currently installed in the pocket area. • At Grigoriou Lambraki street, the urban planning works at the facing…
Μάθε Περισσότερα

November 2016

• At Ethnarchou Makariou street, tramway construction works (earthworks and trackwork) are in progress from Zaimi area up to Papandreou Bridge. • At Mikras Asias street, urban planning works were completed through the execution of planting works, while the works for the construction of the Tramway at the pocket area…
Μάθε Περισσότερα

October 2016

At Ethnarhou Makariou street, the relocation of the storm water pipe in the section from Karaoli & Dimitriou street to Myrtidiotissis street has been completed, while in progress are the Tramway earthworks in the same area. At Mikras Asias street, the works for the construction of the Tramway from Papandreou…
Μάθε Περισσότερα

September 2016

At Ethnarchou Makariou Street, in progress are works for the relocation of the rainwater drainage pipe. At Mikras Asias street, completed are the works for the construction of the tramway corridor from Papandreou Bridge past Sarantaporou Street. The urban planning of the area and Mikras Asias stop is completed. At…
Μάθε Περισσότερα

August 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor at Papandreou Bridge. At Grigoriou Lambraki street, the construction of the tramway corridor from the U-turn up to Venizelou Street, along with the urban planning of Lambraki and Evangelistrias stops are completed. The construction…
Μάθε Περισσότερα