TRAM Project progress

June 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor from Papandreou Bridge up to Sarantaporou street. In progress are the works for the construction of the tramway corridor from Sarantaporou street up to Lambraki Bridge with the U-turn as well as the urban…
Μάθε Περισσότερα

May 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor (from Papandreou bridge up to the U-turn), as well as the urban planning works at the adjacent sidewalk. At Grigoriou Lambraki street, the construction of the tramway corridor at the section extending between Distomou…
Μάθε Περισσότερα

March 2016

In progress are the relocations of OTE & Fiber Optics networks at Ethn. Antistaseos street, street lighting at the sidewalk adjacent to Grigoriou Lambraki street and at the sidewalk adjacent to Ethnikis Antistasseos street. The water supply works commenced by EYDAP and are in progress at the sidewalk adjacent to…
Μάθε Περισσότερα

February 2016

In progress are the relocations of the water supply networks at the sidewalk adjacent to Grigoriou Lambraki street, OTE & Fiber Optics networks at Ethn. Antistaseos street, Sewage & EPA networks at Omiridou Skylitsi street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street and at the sidewalk…
Μάθε Περισσότερα

January 2016

Completed are the relocations of sewage, PPC & and EPA networks at the sidewalk adjacent to Grigoriou Lambraki street, Sewage, EPA & Fiber Optics at Vassileos Georgio street and the ILPAP abolished lines dismantling works at Vassileos Georgiou street. In progress are the relocations of the water supply networks at…
Μάθε Περισσότερα

December 2015

In progress are the relocations of the following PUO networks: EYDAP (water supply and sewage) networks – PPC & and EPA at the sidewalk adjacent to Grigoriou Lambraki street, Sewage – EPA & Fiber Optics at Vassileos Georgiou, EPA at Akti Possidonos, OTE & Fiber Optics at Ethn. Antistaseos street,…
Μάθε Περισσότερα

November 2015

In progress are the relocations of the following PUO networks: EYDAP (water supply and sewage) networks – PPC & and EPA at the sidewalk adjacent to Grigoriou Lambraki street, Sewage – EPA & Fiber Optics at Vassileos Georgiou, EPA at Akti Possidonos, OTE & Fiber Optics at Ethn. Antistaseos street,…
Μάθε Περισσότερα

October 2015

In progress are the relocations of the following PUO networks: sewage and EPA at Vassileos Georgiou, EYDAP (water supply and sewage) networks at the sidewalk adjacent to Grigoriou Lambraki street, sewage and EPA networks at Omiridou Skylitsi street, OTE & fiber optics at Ethn. Antistaseos street & street lighting at…
Μάθε Περισσότερα

September 2015

The works for the relocation of sewage networks at Omiridou Skylitsi street, between Ippodamias & 34th Syntagmatos streets, have been completed. In progress are the relocations of the following networks: sewage and EPA at Vassileos Georgiou concurrently with the archaeological works, EYDAP water supply networks at the sidewalk adjacent to…
Μάθε Περισσότερα

August 2015

Completed are the relocations of OTE networks at the sidewalk of Grigoriou Lambraki street adjacent to the Tramway corridor and the dismantling of ILPAP networks from Ethnikisi Antistasseos Street. In progress are the relocations of sewage and EPA networks along with the archaeological works at Vassileos Georgiou street, as well…