Kalamaria Project progress

  • Home
  • Kalamaria Project progress

September 2024

• NOMARCHIA Station (Station & Crossover): Works for the reinstatement of sidewalks and bollards in Mitropolitou Kydonion Street have been executed. In progress are cabling inspection works of the fire detection system. • KALAMARIA Station: In progress are works for the installation of PSN tiles at level 0, shed and…
Μάθε Περισσότερα
Καλαμαριά

August 2024

• NOMARCHIA Station: In progress are cabling inspection works of the fire detection system. • ARETSOU Station: In progress are works for the installation of floor granites at the platform level as well as cabling inspection works of the fire detection system. • NEA KRINI Station: In progress are cabling…
Μάθε Περισσότερα
Καλαμαριά Ιούλιος 2024

July 2024

• NOMARCHIA Station (Station & Crossover): In the Crossover area, in progress are works for the installation of tiles, as well as works for the waterproofing of the water tank. • ARETSOU Station: In progress are works for the installation of floor granites at the platform level. • MICRA Station:…
Μάθε Περισσότερα
Καλαμαριά Ιούνιος 2024

June 2024

NOMARCHIA Station: Completed are works for the reinstatement of sidewalks and bollards for the protection of pedestrians on Mitropolitou Kydonion street. KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at level 0.…
Μάθε Περισσότερα
Καλαμαριά Μάιος 2024

May 2024

KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, the installation of glass panes at stainless steel rails, as well as works for the installation of PSN tiles at level (-1). ARETSOU Station: Completed are works for the stripping of Kanari Street, while…
Μάθε Περισσότερα
Καλαμαριά Απρίλιος 2024

April 2024

• KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at levels -1 and -2. • ARETSOU Station: In progress are the reinstatement works at street level, as well as works for the…
Μάθε Περισσότερα
Καλαμαριά Μάρτιος 2024

March 2024

KALAMARIA Station: In progress are works for the installation of glass panes at stainless steel rails, PSN tiles at the platform level and at level -2. Moreover, in progress are the works for the installation of cladding at the external escalators. ARETSOU Station: In progress are the reinstatement works at…
Μάθε Περισσότερα
Καλαμαριά Φεβρουάριος 2024

February 2024

• NOMARCHIA Station (Station and Crossover): In the area of the Crossover, completed are the works for the installation of the elevated floor in the signalling equipment room. • KALAMARIA Station: In progress are works for the installation of glass panes at stainless steel rails, PSN tiles at the platform…
Μάθε Περισσότερα
Καλαμαριά Ιανουάριος 2024

January 2024

• NOMARCHIA Station: In progress are works for the implementation of the final traffic reinstatement (configuration of sidewalks at Andrianoupoleos street) as well as works for the installation of stainless steel balustrades and glass panes on stainless steel rails at the platform level. • KALAMARIA Station: In progress are works…
Μάθε Περισσότερα
Καλαμαριά Δεκέμβριος 2023

December 2023

Kritis Shaft: In progress are works for the installation of lighting and low voltage cable distribution trays. NOMARCHIA Station: In progress are works for the implementation of the final traffic reinstatement (configuration of sidewalks at Andrianoupoleos street) as well as works for the installation of stainless steel balustrades and glass…
Μάθε Περισσότερα