Kalamaria Project progress

  • Home
  • Kalamaria Project progress
Καλαμαριά Ιανουάριος 2025

January 2025

NOMARCHIA Station (Station and Crossover): In progress are works for the transfer of switchboards intended for the Medium Voltage System, as well as works for the transfer of the batteries charger unit of the traction power system. MIKRA Station: In progress are the works related to the Medium Voltage distribution…
Μάθε Περισσότερα
Καλαμαριά Δεκέμβριος 2024

December 2024

• NOMARCHIA Station (Station and Crossover): In progress are works for the transfer of switchboards intended for the Medium Voltage System, as well as works for the transfer of the batteries charger unit of the traction power system. • MIKRA Station: In progress are the works related to the Medium…
Μάθε Περισσότερα
Καλαμαριά Νοέμβριος 2024

November 2024

Works for the upgrading of the PSD earthing system, as well as inspection works for the installation of the fire detection system are being executed in all stations.  Moreover, preparatory works for the installation of fibre optics are being executed. NOMARCHIA Station: In progress are the Medium Voltage System related…
Μάθε Περισσότερα
Καλαμαριά Οκτώβριος 2024

October 2024

NEA KRINI Station: In progress are the architectural finishes (walls and ceiling cladding, surfaces painting, stainless steel finishes) related works. MICRA Station: In progress are the architectural finishes (walls and ceiling cladding, surfaces painting, stainless steel finishes) related works, the fire detection system cabling inspection works, as well as road…
Μάθε Περισσότερα

September 2024

• NOMARCHIA Station (Station & Crossover): Works for the reinstatement of sidewalks and bollards in Mitropolitou Kydonion Street have been executed. In progress are cabling inspection works of the fire detection system. • KALAMARIA Station: In progress are works for the installation of PSN tiles at level 0, shed and…
Μάθε Περισσότερα
Καλαμαριά

August 2024

• NOMARCHIA Station: In progress are cabling inspection works of the fire detection system. • ARETSOU Station: In progress are works for the installation of floor granites at the platform level as well as cabling inspection works of the fire detection system. • NEA KRINI Station: In progress are cabling…
Μάθε Περισσότερα
Καλαμαριά Ιούλιος 2024

July 2024

• NOMARCHIA Station (Station & Crossover): In the Crossover area, in progress are works for the installation of tiles, as well as works for the waterproofing of the water tank. • ARETSOU Station: In progress are works for the installation of floor granites at the platform level. • MICRA Station:…
Μάθε Περισσότερα
Καλαμαριά Ιούνιος 2024

June 2024

NOMARCHIA Station: Completed are works for the reinstatement of sidewalks and bollards for the protection of pedestrians on Mitropolitou Kydonion street. KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at level 0.…
Μάθε Περισσότερα
Καλαμαριά Μάιος 2024

May 2024

KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, the installation of glass panes at stainless steel rails, as well as works for the installation of PSN tiles at level (-1). ARETSOU Station: Completed are works for the stripping of Kanari Street, while…
Μάθε Περισσότερα
Καλαμαριά Απρίλιος 2024

April 2024

• KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at levels -1 and -2. • ARETSOU Station: In progress are the reinstatement works at street level, as well as works for the…
Μάθε Περισσότερα