Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Kalamaria Project progress

November 2014

NOMARHIA Station & Crossover: The works concerning the diversion of the 1stbranch of the sewage pipe through TBM underground boring have been completed. The works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp have commenced; KALAMARIA…
Μάθε Περισσότερα

October 2014

NOMARCHIA Station: The works for the construction of shafts for the diversion of the sewage network are in progress; KALAMARIA Station: The works for the diversion of PUO networks are in progress; NEA KRINI Station: The works for the diversion of PUO networks have commenced, while the works for the…
Μάθε Περισσότερα

September 2014

NOMARCHIA Station: The works for the construction of shafts for the diversion of the sewage network have commenced; KALAMARIA Station: The works for the diversion of PUO networks have commenced; MIKRA Station: The excavation and retaining works at the TBMs access shaft are in progress; The preparation of designs is…
Μάθε Περισσότερα

July 2014

The works for the construction of piles for peripheral retaining, as well as excavation works at NEA KRINI Station have commenced; The preparation, review and approval of the designs for the relocation and diversion of PUO networks, the traffic arrangements-diversions and the final designs of the stations are at an…
Μάθε Περισσότερα

May 2014

TBM Start-up Shaft, Micra: The works for the construction of piles and cap beams are in progress. Topographic works at various locations of Kalamaria Extension Project, as well as the preparation, review and approval of the designs for the relocation and diversion of PUO networks, the designs for traffic arrangements-diversions,…
Μάθε Περισσότερα

April 2014

Piles constructed and excavations performed at the TBM start-up shaft at Micra; The Supplementary Geotechnical Survey was completed concerning all locations of the Project; The preparation of designs for the PUO networks relocation and diversion, the designs concerning traffic arrangements – diversions and the final designs are in progress at…
Μάθε Περισσότερα
WCAG