Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Kalamaria Project progress

Καλαμαριά Σεπτέμβριος 2022

September 2022

ARETSOU Station: In progress are works for the installation of the exterior cladding of the escalators, works for the installation of the transformers of the low voltage distribution network and traction power system, as well as works for the installation of steel ducts for the routing of Low Voltage cables…
Μάθε Περισσότερα
Καλαμαριά Αύγουστος 2022

August 2022

NOMARCHIA Station: In progress are works for several settings of the interior escalators and works for the installation of infrastructure for the installation of the platform screen doors. KALAMARIA Station: Completed are works for the installation of transformers in the substation area. ARETSOU Station: In progress are preliminary works for…
Μάθε Περισσότερα
Καλαμαριά Ιούνιος 2022

June 2022

• NOMARCHIA Station: In progress are works for the installation of metal bases for the foundation of transformers at the LAS substation. • KALAMARIA Station: In progress are works for the installation of monorail. • ARETSOU Station: In progress are works for the installation of a network and equipment for…
Μάθε Περισσότερα
Καλαμαριά Μάιος 2022

May 2022

• NOMARCHIA Station (Station and Crossover): In the station area, in progress are works for escalators setting. At the Crossover, in progress are road-paving works as well as works for the installation of protective pipes for the routing of MV cables at the PPC substation. • ARETSOU Station: In progress…
Μάθε Περισσότερα

April 2022

• NOMARCHIA Station (Station & Crossover): In progress are works for the installation of a lift housing structure at street level. In the area of the Crossover in progress are works for the completion of the installation of cylinders of the automatic gas fire suppression system. • ARETSOU Station: In…
Μάθε Περισσότερα
Καλαμαριά Μάρτιος 2022

March 2022

• Kritis Shaft: In progress are works for the installation of tunnel ventilation equipment. • NOMARCHIA Station (Station & Crossover): In progress are works for the installation of Inergen cylinders in the Crossover. • ARETSOU Station: In progress are works for the installation of granite flooring in entrances (surface level)…
Μάθε Περισσότερα
Καλαμαριά - Φεβρουάριος 2022

February 2022

• NOMARCHIA Station (Station and Crossover): In the station, in progress are preliminary works for the installation of Platform Screen Doors (PSD). In the area of the crossover, in progress are works for the installation of ceramic tiles and the installation of trays. • KALAMARIA Station: In progress are works…
Μάθε Περισσότερα
Καλαμαριά Ιανουάριος 2022

January 2022

NOMARCHIA Station (Station and Crossover): In progress are works for the installation of industrial roller shutters, stainless steel balustrades and cabling installation works in the escalators. In the area of the crossover, in progress are works for the construction of sewage network, painting works and works for the installation of…
Μάθε Περισσότερα
Καλαμαριά Οκτώβριος 2012

October 2021

NOMARCHIA Station: In progress are works for the installation of granite tiles on parapet walls and skirting at the central staircase. KALAMARIA Station: In progress are works for the reinstatement of the central island at Pontou street, the installation of glass panes at the east and west entrances, as well…
Μάθε Περισσότερα
Καλαμαριά Νοέμβριος 2021

November 2021

• Kritis Shaft: Preliminary works for the industrial flooring and waterproofing of the station are in progress. • NOMARCHIA Station (Station and Crossover): Reinstatement works at the station street-level are in progress, as well as works for the installation of stainless steel balustrades in the areas where passengers will move.…
Μάθε Περισσότερα
WCAG