Kalamaria Project progress

Καλαμαριά Μάρτιος 2023

May 2023

NOMARCHIA Station: In progress are works for the installation of granites at platform level, works for the construction of the sewage system and the installation of the automatic fire fighting network, as well as works for the installation of rails for the suspension of equipment of the tunnel ventilation system.…
Μάθε Περισσότερα
Καλαμαριά Απρίλιος 2023

April 2023

NOMARCHIA Station: In progress are painting works of the terminations at street level, as well as works for the installation of sound insulations. KALAMARIA Station: In progress are works for the completion of the installation of escalators 3a, 3b & 4a, 4b, as well as works for the construction of…
Μάθε Περισσότερα
Καλαμαριά Μάρτιος 2023

March 2023

Kritis Shaft: In progress are street level reinstatement works and works for the installation of skirting and steel balustrades. NOMARCHIA Station: In progress are painting works of terminations at street-level and works for the installation of the sewage system, while works for the installation of Platform Screen Doors (PSDs) have…
Μάθε Περισσότερα
Καλαμαριά Φεβρουάριος 2023

February 2023

Kritis Shaft: In progress are works for the installation of steel balustrades. NOMARCHIA Station: In progress are works for the installation of Platform Screen Doors (PSDs). KALAMARIA Station: In progress are street level reinstatement works in Pontou street upstream traffic flow, as well as works for the completion of the…
Μάθε Περισσότερα
Καλαμαριά Ιανουάριος 2023

January 2023

Kritis Shaft: In progress are street level reinstatement works, as well as works related to the installation of skirting. NOMARCHIA Station: In progress are granite installation works in the staircases entrances, as well as works for the installation of Platform Screen Doors (PSDs). ARETSOU Station: In progress are preliminary works…
Μάθε Περισσότερα
Καλαμαριά Δεκέμβριος 2022

December 2022

NOMARCHIA Station: In progress are asphalt paving works, as well as the escalators’ setting works and SAT tests. KALAMARIA Station: In progress are works for the installation of stainless steel balustrades and granites at the staircases. ARETSOU Station: In progress are fire detection related works. NEA KRINI Station: In progress…
Μάθε Περισσότερα
Καλαμαριά Νοέμβριος 2022

November 2022

Kritis Shaft: In progress are preparatory works for the installation of steel balustrades, skirting, as well as sealing works of the pumping station. NOMARCHIA Station: In progress are works for the installation of the deluge valve drainage network. KALAMARIA Station: In progress are works for the installation of air-vents of…
Μάθε Περισσότερα
Καλαμαριά Οκτώβριος 2022

October 2022

KALAMARIA Station: In progress are works for the installation of stainless steel balustrades. ARETSOU Station: In progress are works for the installation of the Platform Screen Door (PSD) system. NEA KRINI Station: In progress are works for the installation of storm and waste water pumps, collectors and discharge networks. MIKRA…
Μάθε Περισσότερα
Καλαμαριά Σεπτέμβριος 2022

September 2022

ARETSOU Station: In progress are works for the installation of the exterior cladding of the escalators, works for the installation of the transformers of the low voltage distribution network and traction power system, as well as works for the installation of steel ducts for the routing of Low Voltage cables…
Μάθε Περισσότερα
Καλαμαριά Αύγουστος 2022

August 2022

NOMARCHIA Station: In progress are works for several settings of the interior escalators and works for the installation of infrastructure for the installation of the platform screen doors. KALAMARIA Station: Completed are works for the installation of transformers in the substation area. ARETSOU Station: In progress are preliminary works for…
Μάθε Περισσότερα