Kalamaria Project progress

ΚΑΛΑΜΑΡΙΑ - ΙΑΝΟΥΑΡΙΟΣ 2021

January 2021

  NOMARCHIA Station (Station and Crossover): Reinstatement related works at street level, as well as works for the installation of galvanized balustrades are in progress. KALAMARIA Station: In progress are works for the installation of glass panels of the sheds at the west entrance, as well as works for the…
Μάθε Περισσότερα
KALAMARIA_12_20_1

December 2020

  Kritis Shaft: Reinstatement related works at street level, painting works and works related to the completion of door installation are in progress. KALAMARIA Station: In progress are reinstatement related works at street level, as well as works for the installation of glass panels of the sheds at the east…
Μάθε Περισσότερα

November 2020

  Kritis Shaft: Coloring works and works related to the completion of door installation are in progress. NOMARCHIA Station: In progress are preliminary reinstatement related works at street level, as well as works for the installation of cabling for the lighting network. ARETSOU Station: Infrastructure construction works for irrigation and…
Μάθε Περισσότερα
Πρόοδος έργου Καλαμαριάς - Οκτώβριος 2020

October 2020

  KALAMARIA Station: Landing paving works at the staircase of the eastern entrance and works for the installation of scaffoldings for the installation of glass panels at the sheds of the eastern and western entrances are in progress. In progress are also works for the installation of earthing and cabling…
Μάθε Περισσότερα
Πρόοδος επέκτασης προς Καλαμαριά - Σεπτέμβριος 2020

September 2020

  NOMARCHIA Station: The works for the installation of a steel emergency escape hatch have been completed, while in progress are works for the installation of HVAC equipment. KALAMARIA Station: In progress are works for the construction of network-related infrastructure and works for the implementation of traffic regulations -phase H.…
Μάθε Περισσότερα
Πρόοδος επέκτασης προς Καλαμαριά - Αύγουστος 2020

August 2020

  NOMARCHIA Station: In progress are electrical works and works for the installation of hatches. KALAMARIA Station: In progress are works for the construction of the infrastructure for electromechanical networks at the northeastern section of the station and works for the installation of granites and galvanized barriers at the south…
Μάθε Περισσότερα

July 2020

  Kritis Shaft: Preparatory works for street-level reinstatement are in progress. NOMARCHIA Station: In progress are works for the installation of windows in rooms 2.2 & 2.3, as well as earthing works and works for the installation of air duct networks for HVAC system. KALAMARIA Station: In progress are works…
Μάθε Περισσότερα

June 2020

Kritis Shaft: The works for the construction of masonry walls and plastering works have been completed, while the works for door installation are in progress. NOMARCHIA Station: In progress are the works for the installation of glass doors at platform level and of windows in rooms 2.2 & 2.3, as…
Μάθε Περισσότερα

April 2020

Kritis Shaft: The preliminary works for the construction of masonry walls are in progress. NOMARCHIA Station (station & crossover): The preliminary works for the reinstatement of the surrounding area and the works for the installation of a fire detection network are in progress. KALAMARIA Station: The works for the installation…
Μάθε Περισσότερα

March 2020

NOMARCHIA Station (station & crossover): The works for the installation of granites at the platform level have been completed. KALAMARIA Station: In progress are works for the reinstatement of the surrounding area, the paving of cement mortar for the sub-base of granites at the platform, as well as the works…
Μάθε Περισσότερα