Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Kalamaria Project progress

April 2021

  NOMARCHIA Station (Station and Crossover): Reinstatement related works at street level are in progress. KALAMARIA Station: In progress are works for the installation of special side glass panel items for sheds, as well as reinstatement related works at street level. ARETSOU Station: In progress are surface reinstatement related works.…
Μάθε Περισσότερα

March 2021

  NOMARCHIA Station (Station and Crossover): Works for the installation of manhole covers, reinstatement related works at street level and works for the installation of HVAC system equipment are in progress. KALAMARIA Station: In progress are works for the installation of a metal structure to support the glass panels of…
Μάθε Περισσότερα

February 2021

  NOMARCHIA Station (Station and Crossover): Remaining floor paving works, as well as works for the installation of galvanized balustrades are in progress. KALAMARIA Station: In progress are reinstatement works at street level and works for the installation of glass panels at the sheds of the eastern and western entrance.…
Μάθε Περισσότερα
ΚΑΛΑΜΑΡΙΑ - ΙΑΝΟΥΑΡΙΟΣ 2021

January 2021

  NOMARCHIA Station (Station and Crossover): Reinstatement related works at street level, as well as works for the installation of galvanized balustrades are in progress. KALAMARIA Station: In progress are works for the installation of glass panels of the sheds at the west entrance, as well as works for the…
Μάθε Περισσότερα
KALAMARIA_12_20_1

December 2020

  Kritis Shaft: Reinstatement related works at street level, painting works and works related to the completion of door installation are in progress. KALAMARIA Station: In progress are reinstatement related works at street level, as well as works for the installation of glass panels of the sheds at the east…
Μάθε Περισσότερα

November 2020

  Kritis Shaft: Coloring works and works related to the completion of door installation are in progress. NOMARCHIA Station: In progress are preliminary reinstatement related works at street level, as well as works for the installation of cabling for the lighting network. ARETSOU Station: Infrastructure construction works for irrigation and…
Μάθε Περισσότερα
Πρόοδος έργου Καλαμαριάς - Οκτώβριος 2020

October 2020

  KALAMARIA Station: Landing paving works at the staircase of the eastern entrance and works for the installation of scaffoldings for the installation of glass panels at the sheds of the eastern and western entrances are in progress. In progress are also works for the installation of earthing and cabling…
Μάθε Περισσότερα
Πρόοδος επέκτασης προς Καλαμαριά - Σεπτέμβριος 2020

September 2020

  NOMARCHIA Station: The works for the installation of a steel emergency escape hatch have been completed, while in progress are works for the installation of HVAC equipment. KALAMARIA Station: In progress are works for the construction of network-related infrastructure and works for the implementation of traffic regulations -phase H.…
Μάθε Περισσότερα
Πρόοδος επέκτασης προς Καλαμαριά - Αύγουστος 2020

August 2020

  NOMARCHIA Station: In progress are electrical works and works for the installation of hatches. KALAMARIA Station: In progress are works for the construction of the infrastructure for electromechanical networks at the northeastern section of the station and works for the installation of granites and galvanized barriers at the south…
Μάθε Περισσότερα

July 2020

  Kritis Shaft: Preparatory works for street-level reinstatement are in progress. NOMARCHIA Station: In progress are works for the installation of windows in rooms 2.2 & 2.3, as well as earthing works and works for the installation of air duct networks for HVAC system. KALAMARIA Station: In progress are works…
Μάθε Περισσότερα
WCAG