Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Kalamaria Project progress

SEPTEMBER 2018

Kritis shaft: The works for the construction of the perimeter permanent lining continue, while the works for the construction of connecting tunnels are in progress. NOMARCHIA Station: The works for the construction of platforms are at an advanced stage, while the works for the construction of the lining of indoor…
Μάθε Περισσότερα

AUGUST 2018

Kritis shaft: The works for the construction of forepoles have been completed. NOMARCHIA Station: The works for the construction of the platform are in progress. KALAMARIA Station: Waterproofing works, as well as works for the permanent lining of the east access and pits, are in progress. ARETSOU Station: In progress…
Μάθε Περισσότερα

June 2018

• Kritis shaft: The permanent lining of the pumping station is completed. • NOMARCHIA Station: The permanent lining at section 7 of the perimeter structures (ventilation shafts) and the backfilling and construction of the PUO networks in the area of the north access have been completed. Granite flooring, phase D1…
Μάθε Περισσότερα

May 2018

Kritis shaft: The excavation and temporary retaining of the pumping station have been completed. • NOMARCHIA Station: Completed are the construction of the permanent lining of the north access, as well as the construction of industrial floors at level -2. The backfilling and construction of PUO networks in the area…
Μάθε Περισσότερα

February 2018

• Kritis shaft: The works related to the excavation and temporary retaining of struts down to level -4 have been completed. The excavation and temporary retaining of struts down to level -5 are in progress. • NOMARCHIA Station: The removal of reinforced concrete struts (roof level), as well as the…
Μάθε Περισσότερα

January 2018

Nomarchia Station: The implementation of phase C’ of traffic arrangements and the construction of retaining piles at the north access (at a part of Vas. Olgas street) have been completed. Plastering works are in progress. • KALAMARIA Station: In progress is the construction of the permanent lining and waterproofing of…
Μάθε Περισσότερα

April 2017

NOMARCHIA Station: The permanent lining at level -1 has been completed. Works for the construction of the slab at level -2 are in progress. • KALAMARIA Station: The construction of the permanent lining at level -3 has been completed. The construction of the slab at level -2 is in progress.…
Μάθε Περισσότερα

January 2017

• NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1. • NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level. •…
Μάθε Περισσότερα

November 2016

NOMARCHIA Station: The construction of the permanent lining from the foundation slab up to level -2 is in progress. NOMARCHIA Crossover: The construction of the permanent lining from the foundation slab up to level -1 was completed. In progress is the construction of the slab of level -1 and the…
Μάθε Περισσότερα

October 2016

NOMARCHIA Station: The waterproofing of masonry walls from the foundation slab to level -1 has been completed, while in progress is the construction of the platform. NOMARCHIA Crossover: The waterproofing of masonry walls from the foundation slab to level -1 has been completed. In progress is the construction of scaffolding…
Μάθε Περισσότερα
WCAG