Kalamaria Project progress

September 2016

NOMARCHIA Station: The works for the construction of the foundation slab have been completed. The construction of the permanent lining from the foundation slab up to level -1 is in progress. Nomarchia Junction: The construction of the foundation slab is completed. The removal of the struts at the last level…
Μάθε Περισσότερα

August 2016

NOMARCHIA Station: The works for the construction of the foundation slab are in progress. KALAMARIA Station: The works for the temporary retaining of the metal struts up to the 4th level are in progress. ARETSOU Station: The installation of metal struts at the 2nd level has been completed. In progress…
Μάθε Περισσότερα

June 2016

NOMARCHIA Crossover: The works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert. KALAMARIA Station: The installation of metal struts at the 2nd level have been completed. In progress are the excavation works…
Μάθε Περισσότερα

May 2016

NOMARCHIA Station: The excavation of level -3 of the station, as well as the works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert. NOMARCHIA Crossover: The excavation works of level -3 have…
Μάθε Περισσότερα

March 2016

NOMARCHIA Station: The works for the installation of metal struts at level -2 are in progress. NOMARCHIA Crossover: The works for the installation of metal struts at level -1 were completed. The excavation works of level -2 and the works for the installation of metal struts at level -2 are…
Μάθε Περισσότερα

February 2016

NOMARCHIA Station: The works for the installation of metal struts at level -1 were completed, while the excavation of the station’s level -2 is in progress. NOMARCHIA Crossover: The works for the installation of metal struts at level -1 are in progress. KALAMARIA Station: Works for traffic arrangements – Phase…
Μάθε Περισσότερα

January 2016

NOMARCHIA Station: The excavation of the station’s level -1 is completed, while the works for the installation of metal struts at level -1 are in progress. NOMARCHIA Crossover: The excavation of the crossover’s level -1 is completed, while the works for the installation of metal struts at level -1 are…
Μάθε Περισσότερα

December 2015

NOMARCHIA Station: The construction of struts made of reinforced concrete has been completed, while the excavation of the station’s level -1 is in progress; NOMARCHIA Crossover: The construction of struts made of reinforced concrete has been completed, while the excavation of the crossover’s level -1 is in progress; KALAMARIA Station:…
Μάθε Περισσότερα

November 2015

NOMARCHIA Station: Works for the perimeter piles and piles cap beam have been completed, while the construction of struts made of reinforced concrete at level -1 are in progress. NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam have been completed. The works for the…
Μάθε Περισσότερα

October 2015

NOMARCHIA Station: Works for the phase A excavation, the construction of struts at level -1 and the perimeter piles cap beam are in progress; NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam, as well as works for the diversion of PUO networks are in…
Μάθε Περισσότερα