Kalamaria Project progress

September 2015

NOMARCHIA Station: Works for the excavation of station level -1 and works for the diversion of PUO networks are in progress; NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and works for the diversion of PUO networks are in progress; KALAMARIA Station: Works related to the implementation of…
Μάθε Περισσότερα

August 2015

NOMARCHIA Station: The works for the construction of retaining piles at the perimeter of the station were completed. The works for the construction of a pile cap beam are in progress; KALAMARIA Station: Works for the construction of piles at the western part of the station are in progress; NEA…
Μάθε Περισσότερα

July 2015

NOMARCHIA Station and Crossover: The works for the diversion of PUO networks are in progress. The works for the construction of piles are at an advanced stage; KALAMARIA Station: Works for the construction of temporary retaining piles are in progress; ARETSOU Station: Investigation trenches are in progress; NEA KRINI Station:…
Μάθε Περισσότερα

June 2015

NOMARCHIA Station and Crossover: The works for the construction of temporary retaining piles are at an advanced stage; KALAMARIA Station: Works for the construction of temporary retaining piles are in progress; NEA KRINI Station: Works for the retaining of the station are in progress (installation of struts at the 2nd…
Μάθε Περισσότερα

May 2015

NOMARCHIA Station and Crossover: Construction works for the implementation of the traffic arrangements – Phase A have commenced, while works for the diversion of PUO networks are at an advanced stage. Piling works for the temporary retaining are in progress. The assembly of the building crane has been completed; KALAMARIA…
Μάθε Περισσότερα

April 2015

NOMARCHIA Station and Crossover: Piling works for the temporary retaining and the foundation of the building crane have commenced. Works for the occupation of the worksite are in progress, while works for the diversion of PUO networks are at an advanced stage; KALAMARIA Station: Works for the occupation of the…
Μάθε Περισσότερα

March 2015

The works for the construction of a street parallel to Mitropoliti Kydonion Grigoriou Street within the area of the former Farmaki Military Camp, extending between G. Papandreou and V. Olgas Streets, as well as the works for the construction of a connecting road with Ifigenias Street have been completed. Moreover,…
Μάθε Περισσότερα

February 2015

NOMARCHIA Station & Crossover: The works for the diversion of the central sewage pipe have been completed. At an advanced stage are the works for the construction of a street parallel to Mitropoliti Kydonion Grigoriou Street within the area of the former Farmaki Military Camp, extending between G. Papandreou and…
Μάθε Περισσότερα

January 2015

NOMARHIA Station & Crossover: The works for the construction of pits for the diversion of the central sewage pipe, the works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp, as well as the works for the…
Μάθε Περισσότερα

December 2014

NOMARCHIA Station & Crossover: The works concerning the diversion of the sewage pipe through micro-TBM underground boring have been completed. The works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp, as well as the PUO network…
Μάθε Περισσότερα