Year: 2018

palia eikona 2

NOVEMBER 2018

In the area of PIRAEUS Checks – arrangements – testing of the Tramway corridor, turnouts and catenary and the tramway signaling continue, while the trial operation of the Tramway will commence soon. OTHER WORKS (reference to extensive fronts of works) Along the Tramway route in Piraeus The works for the…
Μάθε Περισσότερα

NOVEMBER 2018

Kritis shaft: The works for the construction of the connecting tunnels are in progress. NOMARCHIA Station: Platform construction works have been completed, while works for the installation of indoor escalators are in progress. KALAMARIA Station: The works for the construction of the south ventilation shaft have been completed, while works…
Μάθε Περισσότερα

NOVEMBER 2018

NEW RAILWAY Station: The works for the installation of ceramic tiles in other station levels as well are at an advanced stage. DIMOKRATIAS Station (Station and Crossover): Floor cladding works using granite slabs are in progress. VENIZELOU Station: Works for burring of archaeological finds and archaeological survey related works at…
Μάθε Περισσότερα

NOVEMBER 2018

Komninou Shaft: Architectural works are in progress. AGHIA VARVARA Station: At ticketing level walls, at the staircases and the landings the works for the installation of granite slabs are in progress. Meg. Alexandrou Shaft: Completed are masonry and plastering works, as well as the works for the installation of doors…
Μάθε Περισσότερα

ATTIKO METRO: “With an eye to the future” Commencement of the Training Program “The Metro in our City”

ATTIKO METRO S.A.: “With an eye to the future” Commencement of the Training Program “The Metro in our City”   ATTIKO METRO S.A. invites you to the Children’s Museum of Thessaloniki on Saturday, November 10th 2018, at 10:30, to attend the commencement of the training program “The Metro in our…
Μάθε Περισσότερα
AM_TRAM_Oct2018-

OCTOBER 2018

In the area of PIRAEUS Checks – arrangements – testing of the Tramway corridor, turnouts and catenary have commenced, while the trial operation of the Tramway will commence soon. OTHER WORKS (reference to extensive fronts of works) Along the Tramway route in Piraeus The works for the installation of E/M…
Μάθε Περισσότερα

OCTOBER 2018

Kritis shaft: The works for the construction of the connecting tunnels are in progress. NOMARCHIA Station: The painting works are completed. KALAMARIA Station: The works for the permanent lining of the eastern access of the Station are in progress. ARETSOU Station: The works for the concreting and waterproofing of the…
Μάθε Περισσότερα

OCTOBER 2018

TBM Access Shaft: The works for the waterproofing of the perimeter walls have been completed. Komninou Shaft: The works for the excavation and temporary retaining of the shaft and the connecting tunnel, as well as the works related to masonry, cladding, installation of doors and industrial floors have been competed.…
Μάθε Περισσότερα

OCTOBER 2018

NEW RAILWAY Station: The works for the construction of indoor partitions are in progress. DIMOKRATIAS Station (Station and Crossover): The works for closing the southern opening, as well as for the reinstatement of the southern sidewalk of Monastiriou street are in progress. Works related to the implementation of the next…