Year: 2018

February 2018

[responsivevoice_button voice=”UK English Female” buttontext=”Listen to post”] NEW RAILWAY Station: Implementation of traffic phase E’, as well as plastering and masonry wall related works have been completed. The works for the construction of shaft terminations are in progress. • AGHIA SOFIA Station – north access: The archaeological excavation in progress.…
Μάθε Περισσότερα

February 2018

A. With regard to the TRAMWAY CORRIDOR: In the remaining areas of the entire Tramway network: • Tramway corridor works have been completed: – at N. Faliro stop (installation of turnouts and connection of the Tramway extension to Piraeus with the operating tramway network) – at Mousson Street (installation of…
Μάθε Περισσότερα

February 2018

• AGHIA VARVARA Station – Doors painting works and waterproofing works are in progress. • KORYDALLOS Station – Access 2 excavation works are in progress. Pissidias shaft: Excavation works and works for the installation of the temporary retaining system, foundation improvement and temporary retaining works have been completed. Excavation works…
Μάθε Περισσότερα

January 2018

Nomarchia Station: The implementation of phase C’ of traffic arrangements and the construction of retaining piles at the north access (at a part of Vas. Olgas street) have been completed. Plastering works are in progress. • KALAMARIA Station: In progress is the construction of the permanent lining and waterproofing of…
Μάθε Περισσότερα

January 2018

NEW RAILWAY Station: The installation of escalators at the accesses has been completed. In progress are works for the implementation of traffic phase E’, as well as the works for the installation of doors and E/M installations (sewage network). • DIMOKRATIAS Station: The construction of the north access and the…
Μάθε Περισσότερα

January 2018

A. With regard to the TRAMWAY CORRIDOR: • The following works have been completed: Tramway corridor (trackwork – rails, infrastructure works for multiple ducts and foundation of catenary poles) – at Ethnarhou Makariou street (from N. Faliro stop –connection with the beginning of the extension- to Papandreou bridge) – at…
Μάθε Περισσότερα

January 2018

• TBM access shaft: The works for the construction and waterproofing of perimeter walls has been completed. • AGHIA VARVARA Station – M. Alexandrou shaft: The works for the permanent lining of the shaft’s wall are in progress. • KORYDALLOS Station – Pissidias shaft: Excavation and temporary retaining works (levels…
Μάθε Περισσότερα