Year: 2019

APRIL 2019

Α. Tramway The works for the construction of the tramway corridor (trackwork – rails – catenary) have been completed. The following works are in progress: The trial run of the Tramway system and the adjustment – checking of the systems and devices controlling the operation of the Tramway system (for…
Μάθε Περισσότερα

APRIL 2019

– TBM access shaft: The waterproofing of the ceiling slab +62.86 has been completed. – Komninou shaft: The works for the staircase balustrade have been completed, while architectural works (hatch construction) are in progress. AGHIA VARVARA Station: The works for the installation of granite slabs on the floor and walls…
Μάθε Περισσότερα

MARCH 2019

Α. Tramway The works for the construction of the tramway corridor (trackwork – rails – catenary) have been completed. The trial run of the Tramway system has commenced. Setting – checking of the systems controlling the operation of the Tramway system extension to Piraeus from the Central Control Room in…
Μάθε Περισσότερα

MARCH 2019

– TBM access shaft: The installation of an indoor steel plate has been completed. – Komninou shaft: Surface reinstatement is in progress. – Megalou Alexandrou shaft: Surface reinstatement is in progress. – Pissidias shaft: The final lining of Pissidias Shaft has been completed, screed placing at the treads of the…
Μάθε Περισσότερα

FEBRUARY 2019

Piraeus TBM access shaft: The construction of slabs at levels +47.46 and +56.11 has been completed, while the surface reinstatement is in progress. Komninou shaft: The installation of a grid at street level has been completed, while the architectural works (manufacturing of balustrades) are in progress. AGHIA VARVARA station: The…
Μάθε Περισσότερα