Year: 2020

Επίσκεψη στον υπό κατασκευή σταθμό «Αγ. Βαρβάρα»

Visit of political officials of the Ministry of Infrastructure and Transport to AGHIA VARVARA Line 3 Metro Station under construction

[responsivevoice_button voice=”UK English Female” buttontext=”Listen to post”] The Minister of Infrastructure and Transport Kostas Karamanlis, together with the Deputy Minister Yiannis Kefalogiannis and the Secretary General of Infrastructure George Karayiannis visited today AGHIA VARVARA Station, in Metro Line 3 Extension “Aghia Marina – Dimotiko Theatro”, currently under construction, which will…
Μάθε Περισσότερα

April 2020

Kritis Shaft: The preliminary works for the construction of masonry walls are in progress. NOMARCHIA Station (station & crossover): The preliminary works for the reinstatement of the surrounding area and the works for the installation of a fire detection network are in progress. KALAMARIA Station: The works for the installation…
Μάθε Περισσότερα

April 2020

NEW RAILWAY STATION: The works for the construction of the filling concrete in the area of the forestation are in progress. DIMOKRATIAS Station: The works for the installation of a sewage network are in progress. VENIZELOU Station: The works for the removal of struts and monorail installation are in progress.…
Μάθε Περισσότερα

APRIL 2020

AGHIA VARVARA STATION  The following works are in progress: Wall and columns cladding (metal, glass etc.) Square reinstatement (installation of marbles) Other reinstatement works at street level Station signs and other signs Installation of metal false ceilings Architectural finishes (installation of balustrades and handrails) Other architectural finishes. MEGALOU ALEXANDROU SHAFT…
Μάθε Περισσότερα

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform. DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed…
Μάθε Περισσότερα

March 2020

NOMARCHIA Station (station & crossover): The works for the installation of granites at the platform level have been completed. KALAMARIA Station: In progress are works for the reinstatement of the surrounding area, the paving of cement mortar for the sub-base of granites at the platform, as well as the works…
Μάθε Περισσότερα

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform. DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed…
Μάθε Περισσότερα

February 2020

NOMARCHIA Station (station & crossover): In progress are the works for the installation of granites at the platform level, as well as the works related to sewage, earthing of electric trays and piping of the lighting network, power distribution and low voltage (weak currents) networks. KALAMARIA Station: In progress are…
Μάθε Περισσότερα

February 2020

NEW RAILWAY Station: In progress are the works related to the lift installation and the construction of filling concrete and sidewalk base. PAPAFI Station: The works for the installation of Platform Screen Doors (PSD) have been completed. In progress are earthing construction works. FLEMING Station: In progress are the works…
Μάθε Περισσότερα

January 2020

Kritis Shaft: The works for the construction of the permanent lining are in progress. NOMARCHIA Station (station & crossover): The works for the installation of galvanized balustrades and handrails are in progress. Moreover, in progress are the works for the installation of ventilation equipment, fire-rated air ducts, fire fighting networks…
Μάθε Περισσότερα