TZAVELA Shaft  The following works have been completed: Permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Traffic Arrangement – Phase B’. Installation of doors. The following works are in progress: Reinstatement works at Tzavela and Lakonias Streets (installation of curbs, construction of gutters,…
Μάθε Περισσότερα
Καλαμαριά Αύγουστος 2021

August 2021

KALAMARIA Station: Preliminary works for the implementation of the 10th traffic arrangement and works for the installation of lighting fixtures and tray earthing works are in progress. NEA KRINI Station: Surface reinstatement works and works for the installation of lighting fixtures and tray earthing works are in progress. MICRA Station (Station & Crossovers): Works for the…
Μάθε Περισσότερα
Θεσσαλονίκη Αύγουστος 2021

August 2021

New Railway Station: Works for the installation of fire-rated air ducts at the platform level have been completed. DIMOKRATIAS Station: Surface reinstatement works at the north section have been completed and the section has already been delivered for use to the public. In progress are marble cladding works at level -1 and…
Μάθε Περισσότερα
Πειραιάς Ιούλιος 2021

AUGUST 2021

TZAVELA Shaft The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Traffic Arrangement – Phase B’ The following works are in progress: Reinstatement works at Tzavela and Lakonias Streets (installation of curbs, construction of gutters,…
Μάθε Περισσότερα
Καλαμαριά Ιούλιος 2021

July 2021

NOMARCHIA Station (Station & Crossover): Street-level reinstatement works, works for the installation of stainless steel balustrades and handrails at the entrance staircase and works for the installation of lighting fixtures are in progress. At the crossover, concreting works of the roof slab for closing of the opening and waterproofing works are in progress. KALAMARIA Station:…
Μάθε Περισσότερα
Θεσσαλονίκη Ιούλιος 2021

July 2021

NEW RAILWAY STATION: In progress are works for the installation of cable trays at the Forestation tunnel, as well as works for the configuration of the surrounding area at the northern section of the station. DIMOKRATIAS Station: Completed are works for the closing of the temporary opening of the roof slab, as…
Μάθε Περισσότερα
Πειραιάς Ιούλιος 2021

JULY 2021

TZAVELA Shaft  The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Traffic Arrangement – Phase B’ The following works are in progress: Reinstatement works at Tzavela and Lakonias Streets. MANIATIKA STATION STATION’s OPEN CUT       The…
Μάθε Περισσότερα

Thessaloniki Metro Development Study

In the framework of the updated Transport Plan with a 20-year planning horizon, ATTIKO METRO S.A. is developing the Metro Network Development Plan in Thessaloniki based on the results of the project “Thessaloniki Metro Development Study (TMDS)”. The preparation of the subject Study, which takes into consideration the entire Urban Cluster and the…
Μάθε Περισσότερα

THESSALONIKI METRO: VENIZELOU STATION – Traffic arrangements

VENIZELOU Station Traffic arrangements   In view of the execution of the works related to the construction of VENIZELOU Station neighboring with Hamza Bey (Alcazar), the following traffic arrangements shall be put into effect as of Tuesday July 27th 2021: Vehicular traffic shall be interrupted at the north section of Eletheriou Venizelou Steet from its junction with Egnatia Street up to Christou Vamvaka Street. Vehicular traffic at the north branch of Eleftheriou Venizelou is reinstated through Antigonidon Street. Alternatively, Halkeon…
Μάθε Περισσότερα
Καλαμαριά Ιούνιος 2021

June 2021

NOMARCHIA Station (Station & Cross Over): At the cross-over, concreting works at the intermediate slab for closing of the opening are in progress. ARETSOU Station: Surface reinstatement works are in progress. MICRA Station (Station & Cross Overs): In the area of the 2nd cross-sections, in progress are surface reinstatement works and works for the installation of the fire-fighting system. TRACK WORK In progress are works…