NEW RAILWAY Station: The installation of escalators at the accesses has been completed. In progress are works for the implementation of traffic phase E’, as well as the works for the installation of doors and E/M installations (sewage network).
• DIMOKRATIAS Station: The construction of the north access and the excavation and construction of the temporary retaining at the south access have been completed. In progress are works for the construction of the south access, as well as painting works.
• VENIZELOU Station: In progress are archaeological works executed near the area where works for the construction of micropiles for the retaining system of the station are in progress, at the main Station shafts, and where works for the diversion of PUO networks at the south access are under execution.
• SINTRIVANI Station – EXPO: Completed is the detachment of the tomb structure at the south access. In progress are painting works, door installation works, as well as works for the excavation and temporary retaining of the final level at the south access.
• PANEPISTIMIO Station: Works for the waterproofing of pits and accesses, floors and E/M installations are in progress.
• PAPAFI Station: The E/M installation works and the works for the implementation of traffic phase E’ are in progress.
• FLEMING Station: The construction of floors is in progress.
• ANALIPSEOS Station & Crossover: Wall plastering works, plastering works at the staircase of ventilation shaft 3, as well as E/M installation works are in progress.
• 25 MARTIOU Station & Crossover: In progress are the excavation of the east emergency exit, the installation of escalators and the construction of staircases and sidewalks at the crossover.
• NEA ELVETIA Station and Crossover: In progress are wall plastering and re-backfilling works.
• Depot – Building Complex I: In progress are works for the installation of door frames, the construction of gypsum board partition walls and lining, terrace insulation and E/M installations (cable trays, sewage). Building Complex II: The following works are in progress: painting works, as well as works for the installation of panels and doors in the OCC; construction of the platform and parapet walls at section VI; painting works using fire resistant paint for the metal structure at section IV; installation of power supply ducts and sewage piping at the platforms. In the surrounding area, in progress are the works for the construction of networks and manholes in the track area between building 1 and the OCC.
• TBM Tunnels: In progress are tunnel waterproofing works and works for the construction of tunnel filing concrete from ANALIPSI Station to AGHIA SOFIA Station.
• Cut & Cover (C&C) and NATM Tunnels – Section I: In progress are works for backfilling (Sections II, III, V) and reinstatement of PUOs (II, III).