February 2018

• Kritis shaft: The works related to the excavation and temporary retaining of struts down to level -4 have been completed. The excavation and temporary retaining of struts down to level -5 are in progress.

• NOMARCHIA Station: The removal of reinforced concrete struts (roof level), as well as the excavation and retaining up to the 1st row of struts at the north access (at a part of Vas. Olgas Avenue) have been completed. The excavation of the north access (at a part of Vas. Olgas Avenue) and the backfilling of the widenings are in progress.

• NOMARCHIA Crossover: The construction of floors is in progress.

• ARETSOU Station: The construction of the station is in progress.

• NEA KRINI Station: Masonry works are in progress.

• MIKRA Station (& crossovers) – 2nd crossover: Works related to the waterproofing of the roof slab and masonry works have been completed. Plastering works are in progress.

• MIKRA Forestation: The construction of the permanent lining has been completed. Waterproofing works are in progress (sections 1 and 2).

• Terminal Shaft: The construction of the permanent lining has been completed, while the construction of the staircase inside the shaft is in progress.

• TBM tunnels: Completion of tunnel 2 boring works along “Kalamaria- Nomarchia” tunnel section by TBM2 (‘Elli’). In progress is tunnel 1 boring works along “Kalamaria-Nomarchias Crossover” tunnel section by TBM1 (“Frixos”).