SEPTEMBER 2018

  • Two-track NATM tunnel: The works for the permanent lining of the tunnel’s vault have been completed.
  • TBM Access Shaft: The works for the excavation and temporary retaining of the shaft have been completed together with the works for the construction of the foundation slab and the perimeter walls.
  • Komninou Shaft: The works for the permanent lining of the connecting tunnel of the shaft have been competed.
  • AGHIA VARVARA Station: Granite installation works at concourse level and works for the installation of steel doors are in progress.
  • KORYDALLOS Station: Works for the installation of granites, masonry wall works are at an advanced staged, while floor screeding works, industrial flooring and other special flooring works are in progress.
  • NIKEA Station: Supplementary works for the construction of the non-bearing masonry walls at the platform level-3 are in progress, while E/M works are also in progress.
  • NATM Gallery of NIKEA: Works for the waterproofing of the gallery invert have been completed, together with the works for the excavation and temporary retaining of the gallery.
  • MANIATIKA Station: The works for the permanent lining of the foundation in the pumping station are at an advanced stage, while works for the permanent lining of the E/M slab and of the mezzanine floor slab have been completed.
  • PIRAEUS Station: The works for the installation and pre-stressing of the retaining struts have been completed, while works for the excavation of the 4th level of the main station are at a completion stage, and works for the installation of pre-stressing struts at this level are in progress.
  • ROLOI Shaft: Works for the diversion of stormwater network have been completed.
  • DIMOTIKO THEATRO Station: At the underground section of the station, concreting works at the floor, walls and the vault have been completed, while reinforcement, formwork and concreting works at the platform walls are at an advanced stage.