In PIRAEUS
- The works for the Multi-Channelled Layout and the Overhead Traction Line are at a completion stage.
- Civil works have been completed, while E/M works in the new Substation no. 16 are on hold.
OTHER WORKS (extensive fronts of works)
Along the Tramway route in Piraeus
- The works for the reinstatement of the urban equipment at the Tramway stops and the works for the maintenance of shafts on the road pavement are in progress.
At Vassileos Georgiou Street
- In the area extending between Philonos and Miaouli Streets, urban planning works for the configuration of sidewalks are at a completion stage.
- At SEF tramway stop and in Alikanou Square urban planning works for the configuration of sidewalks are at an advanced stage.
- In several areas of Piraeus, 130 shafts have already been constructed and 116 underground waste bins have been installed, while the delivery of the remaining waste bins in the Municipality is in progress.