Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

OCTOBER 2018

    • TBM Access Shaft: The works for the waterproofing of the perimeter walls have been completed.
    • Komninou Shaft: The works for the excavation and temporary retaining of the shaft and the connecting tunnel, as well as the works related to masonry, cladding, installation of doors and industrial floors have been competed.
  • AGHIA VARVARA Station: At ticketing level, works for the installation of granite slabs and of false ceilings made of mineral fibers have been completed.
    • Meg. Alexandrou Shaft: Completed are the excavation and temporary retaining works of the shaft and the connecting tunnel, as well as the permanent lining of the connecting tunnel, the shaft and the staircase.
    • Taxiarchon Shaft: Filling works and works for the construction of industrial floors are in progress.
  • KORYDALLOS Station: Works for the waterproofing and permanent lining of the Station accesses are in progress.
    • Pissidias Shaft: The final lining of the foundation slab of the Shaft, as well as the excavation of the temporary retaining of NATM Ventilation Gallery, have been completed.
  • NIKEA Station: The construction of the final lining of parapet walls and the vault between the 1st and the 2nd contraction joints in the Station’s NATM ventilation gallery has been completed, while in progress are the works for the construction of the final lining of parapet walls between the 2nd and the 3rd contraction joints.
    • North Station Access: The works for the waterproofing and the construction of the permanent lining have been completed.
  • MANIATIKA Station: The works for the permanent lining of columns parapet walls from the E/M slab level (-3) to the ticketing slab level (-2) are in progress.
    • Roloi Shaft: Excavation and temporary retaining works down to -5m are in progress.
  • DIMOTIKO THEATRO Station: Formwork – reinforcement works of the roof slab in the main station are at an advanced stage, while concreting works of the perimeter wall and of the E/M roof slab up to the roof slab are in progress.
WCAG