Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

NOVEMBER 2018

    • Komninou Shaft: Architectural works are in progress.
  • AGHIA VARVARA Station: At ticketing level walls, at the staircases and the landings the works for the installation of granite slabs are in progress.
    • Meg. Alexandrou Shaft: Completed are masonry and plastering works, as well as the works for the installation of doors and the placement of industrial floor.
  • KORYDALLOS Station: Works for the installation of doors are in progress, while works for the installation of ceramic tiles and granites and backfilling works are in progress.
    • Pissidias Shaft: Works for the construction of the final lining of outer perimeter walls at the main Shaft are in progress.
  • NIKEA Station: Completed are the construction, excavation and temporary retaining of the station, as well as the waterproofing and the construction of the final lining of the invert.
  • North Station Access: Completed are the works for the demolition of the pile cap beam and backfilling works.
    • Tzavela Shaft: In progress are excavation works and works for the temporary retaining of the shaft, while traffic diversion works and works for the construction of the perimeter pile cap beam have been completed.
  • MANIATIKA Station: The works for the permanent lining of staircases S1, S3 and S4 and works for the permanent lining of walls and columns from the E/M slab level (-3) to the ticketing slab level (-2) are in progress.
  • Main Tunnel of Station (NATM): The works for the earthing of the main tunnel of the station and the relevant waterproofing works are in progress.
  • PIRAEUS Station: The excavation of the 1st, 2nd, 3rd and 4th level has been completed, while works for the excavation of the 5th level of the main station is in progress. Works for the installation and pre-stressing of the struts at the 4th level are in progress.
    • Roloi Shaft: Excavation and temporary retaining works down to -9.00m are in progress.
  • DIMOTIKO THEATRO Station: The works for the concreting of the roof slab (axis 8-10) and the works for the waterproofing-installation of reinforcement at the junction with the TBM tunnel (track level up to platform level) are at an advanced stage.
WCAG