Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

NOVEMBER 2018

    • Kritis shaft: The works for the construction of the connecting tunnels are in progress.
  • NOMARCHIA Station: Platform construction works have been completed, while works for the installation of indoor escalators are in progress.
  • KALAMARIA Station: The works for the construction of the south ventilation shaft have been completed, while works for the construction of the east entrance and the construction of the north ventilation shaft are in progress.
  • ARETSOU Station: The works for the installation of indoor escalators have been completed, while painting works and platform construction works are in progress.
    • Pontou Shaft: The works for the construction of the permanent lining and the construction of the 2nd connecting tunnel are in progress.
  • NEA KRINI Station: Works for the construction of indoor walls lining and the construction of E/M installations are in progress.
  • MIKRA Station (Station & Crossovers): The works for the installation of ceramic tiles at the station have been completed, while masonry woks and floor cladding works using granite slabs in the station are in progress.
    • Forestation: Masonry works have been completed, while plastering works are in progress.
    • TBM tunnels: The disassembly and removal of both TBMs have been completed, as well as the works for the removal of the TBM worksite related facilities from the tunnels. The construction of pumping stations related works are in progress.
WCAG