DECEMBER 2018

    • Komninou Shaft: Architectural works are in progress.
  • AGHIA VARVARA Station: The wall cladding works and the works for the installation of columns have been completed, while the works for the installation of false ceiling system supports at the ticketing level are in progress.
    • Meg. Alexandrou Shaft: Architectural works are in progress.
  • KORYDALLOS Station: In progress are works for the installation of the permanent lining of the Station accesses, as well as works for the dismantling of piles and the cap beam.
  • NIKEA Station: The construction of the permanent lining of the main station, as well as the construction of the permanent lining of NATM tunnel have been completed. Moreover, painting works of the technical rooms of the Station – Phase A’ – have been completed.
  • MANIATIKA Station: The works for the permanent lining of the foundation at level -4 and the permanent lining of the E/M slab at level -3 have been completed, while the works for the permanent lining of the slab at the mechanical floor (-1) are in progress.
    • PIRAEUS Station: Works for the installation and pre-stressing of struts for the temporary retaining of the 1st, 2nd, 3rd and 4th levels have been completed.
    • Roloi Shaft: The works for the diversion of the storm water network have been completed.
  • DIMOTIKO THEATRO Station: The waterproofing and concreting of the floor, walls and the vault in the framework of the permanent lining at the southern staircase have been completed, while the secondary concreting works are in progress.