DECEMBER 2018

  • NEW RAILWAY Station: The works for the installation of ceramic tiles continue.
  • DIMOKRATIAS Station (Station and Crossover): The reinstatement of the southern sidewalk at Monastiriou street (at the crossover), as well as the implementation of traffic phase L’ have been completed. Floor cladding works using granite slabs are in progress.
  • VENIZELOU Station: Works for burring of archaeological finds and archaeological survey related works at the west and east ends continue.
  • AGHIA SOFIA Station: Completed is the removal of the fire chamber of the public baths at the southern access of the station, as well as the construction of the temporary retaining at the southern ventilation shaft.
  • SINTRIVANI Station: Painting works and works for the configuration of the surrounding area are in progress.
  • PANEPISTIMIO Station: Wall cladding works using granite slabs continue.
  • PAPAFI Station: The works for the construction of parapet walls made of gypsum boards are in progress, while wall cladding works using granite slabs continue.
  • EFKLIDIS Station: Painting works and E/M installation works continue.
  • FLEMING Station: Wall cladding works using granite slabs, as well as E/M installation works are at an advanced stage.
  • ANALIPSI Station (station & crossover): Works for the construction of masonry walls at the platform level, as well as works for the construction of parapet walls using gypsum boards are in progress.
  • 25 MARTIOU Station (station & crossover): Works for the construction of masonry walls at track level are at an advanced stage.
  • VOULGARI Station: Works for the reinstatement and configuration of the surrounding area are in progress.
  • NEA ELVETIA Station: Works for the construction of industrial floors are in progress.
    • Depot:
      • Building Complex Ι: The works for the installation of rack system at the warehouse have been completed.
      • Building Complex ΙΙ: The works for the construction of gypsum boards, the insulation of small structures on the roof, as well as the construction of metal sheds’ roof are in progress.
    • ΤΒΜ tunnels: The works for the construction of pumping stations and the construction of trackwork at a section of the tunnels continue.
    • C&C and NATM tunnels: Works for the reinstatement of the surrounding area at surface level, roadworks, works for the construction of sidewalks and backfilling works are at an advanced stage.