NEW RAILWAY Station: The E/M installation works, as well as flooring works using granite slabs are in progress.

DIMOKRATIAS Station (Station and Crossover): The works for the delivery of the worksite area at the north side of Egnatia street, as well as the E/M installation and painting works are in progress.

VENIZELOU Station: The station construction works are progressing. Works for burring of archaeological finds are under completion. Archaeological survey related works at both shafts (west and east) are under completion, while the construction of the station’s roof slab will commence very soon.

AGHIA SOFIA Station: The implementation of traffic phase F’, as well as the archaeological investigation at the north access, have been completed. The construction of slab at level -1 and the temporary retaining of the north and south access are in progress. Moreover, in progress is the archaeological excavation at the south access and at the new south ventilation shaft.

SINTRIVANI Station/EXPO: Wall cladding works using granite slabs at the south access, as well as works for the installation of lifts, are in progress.

PANEPISTIMIO Station: Wall and floor cladding works using ceramic tiles are in progress.

PAPAFI Station: Painting works and works for the installation of acoustic panels at the ventilation shafts are in progress.

EFKLIDIS Station: Wall cladding works using ceramic tiles and granite, as well as E/M installation works are in progress.

FLEMING Station: Cladding works using granite slabs are in progress.

ANALIPSI Station (station & crossover): Flooring works using granite slabs and ceramic tiles are in progress.

25 MARTIOU Station (station & crossover): E/M installation works, as well as flooring works using granite slabs are in progress.

VOULGARI Station: Flooring works using granite slabs and ceramic tiles are in progress.

NEA ELVETIA Station (station & crossover): E/M installation works, as well as flooring works using granite slabs are in progress.

DEPOT:

Building Complex ΙΙ: Trackwork is in progress.
C&C and NATM tunnels: Works for the reinstatement of the surrounding area at surface level are in progress.