Piraeus
- TBM access shaft: The construction of slabs at levels +47.46 and +56.11 has been completed, while the surface reinstatement is in progress.
- Komninou shaft: The installation of a grid at street level has been completed, while the architectural works (manufacturing of balustrades) are in progress.
- AGHIA VARVARA station: The cladding of walls and columns, as well as the reinstatement at street – square level (0) are in progress.
– Megalou Alexandrou shaft: The works for the installation of a grid at street level have been completed, while the architectural works (manufacturing of balustrades) are in progress.
- KORYDALLOS station: The installation of false ceilings is in progress.
– Pissidias shaft: The final cladding of the central wall and of the staircase of the main Shaft is in progress.
- NIKEA station: The painting works (Phase B’) of the Station’s technical rooms, as well as the preliminary works for the installation of the false ceiling metal panels on the roofs of the Station’s levels -3 and -4 are in progress.
- MANIATIKA station: At the Station’s C/C, the permanent lining of staircase S4 has been completed, while the works for the permanent lining of the mezzanine floor slab are in progress.
– Main tunnel of the station: The works for the permanent cladding of the north headwall, as well as the dismantling of the temporary concrete in the deepening area are in progress.
– Underground NATM sections of the station: The permanent lining of the SE, the NW and the NE access tunnel is in progress.
– Mela shaft: The worksite fencing related works are in progress.
- PIRAEUS station: The works for the installation and pre-stressing of struts at the 5th level are in progress.
– Roloi shaft: The construction of the foundation has been completed, while the concreting of the permanent lining of the perimeter walls is in progress.
- DIMOTIKO THEATRO station: At the Main Station, at Aghiou Konstantinou square, the masonry works at the E/M & Concourse levels, as well as the painting works of industrial floors at the mechanical floor level are in progress. The installation of reinforcement at the perimeter walls located in the connecting area with the TBM tunnel is in progress.
– Staircase galleries: At the South Staircase, the works for the installation of secondary concrete are in progress.
– Entrance of Korai square: Works for the waterproofing and concreting of the permanent lining are in progress.
– Double track TBM Tunnel, in Electrical Recess 3RP3 KP 8+707.585: The concreting of the permanent lining (2/14m) is still pending, while the excavation – temporary retaining (progress/phase A’ 8/14, phase B’ 2/14) is in progress.
– Deligianni shaft: Works for the waterproofing of perimeter walls are in progress.
- Panepistimio shaft: The concreting of the permanent lining is on hold (the pumping station flooring is completed).