NEW RAILWAY Station: The works for the reinstatement of the surrounding area at street level are in progress.
VENIZELOU Station: The works for the construction of the station’s roof are in progress.
AGHIA SOFIA Station: The works for the construction of the slab at level -2 have been completed. In progress is the excavation of the station up to the final level of the station, the construction of inner walls and staircases, as well as the construction of the waterproofing at the northern access.
SINTRIVANI Station/EXPO: The works for the installation of the handrails of the exterior escalators are in progress.
PANEPISTIMIO Station: E/M works are in progress.
EFKLIDIS Station: Parapet wall cladding works using granite slabs, as well as works for the construction of exterior canopies are in progress.
FLEMING Station: Vertical cladding works using granite slabs are in progress.
ANALIPSI Station (Station & Crossover): Vertical cladding works using granite slabs, as well as works for the installation of soundproofing system in technical rooms are in progress.
25 MARTIOU Station (Station & Crossover): Works for the installation of soundproofing system in technical rooms are in progress.
VOULGARI Station: E/M works are in progress.
DEPOT:
Building Complex ΙΙ: In progress are the following works: construction of skylights on the metal roof, installation of the sub-frames for covering side-structures on the west façade, the construction of a system covering the metal roof, as well as the installation of tiles in WCs. Moreover, in progress are the works for the installation of the 3rd rail and the construction of E/M infrastructure works, of inner roads and of the exterior fencing of the Depot.
TBM tunnels: The E/M installations at a tunnel section are in progress.
C&C and NATM tunnels: The construction of invert filling concrete in the C/C tunnel is in progress.