Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

OCTOBER 2019

DOUBLE TRACK ΝΑΤΜ START TUNNEL

Works have been completed.

KOMNINOU SHAFT

The following works have been completed:

  • Masonry works, plastering works, door installation, industrial floor, painting works, installation of grids at street level, staircase balustrades, hatch
  • Reinstatement at street level

AGHIA VARVARA STATION

The following works are in progress:

  • Reinstatement at street level – Square level (fountain)
  • Cladding of walls and columns (steel, glass, etc.)
  • Installation of roller shutters
  • Installation of handrails
  • Other architectural finishes

MEGALOU ALEXANDROU SHAFT

 Works have been completed.

KORYDALLOS STATION

The following works are in progress:

  • Door installation
  • Ceramic tiles installation
  • Granite or marble installation
  • Handrail installation
  • Balustrades installation

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Final reinstatement (slab paving) at the station street level (– 0).
  • Wall cladding with granite slabs at platform level (– 3).
  • E/M works

DIMOTIKO THEATRO STATION

MAIN STATIONAGHIOU KONSTANTINOU SQUARE

 The following works are put on hold:

  • Door installation at E/M level

The following works are in progress:

  • Preservation of the archaeological finds of the Project
  • Opening of an exhibition area for the display of the project’s archeological finds at the building located at Pylon Street owned by the Directorate of Antiquities

ENTRANCE TO KORAI SQUARE AND ACCESS TUNNEL

 The following works are in progress:

  • Construction of a lift termination

DOUBLE TRACK TBM TUNNEL

 Works have been completed.

TRIPLE TRACK NATM TUNNEL

DIRECTION UNIVERSITY OF PIRAEUS

The following works have been completed:

  • Construction of permanent lining
WCAG