DOUBLE TRACK ΝΑΤΜ START TUNNEL
Works have been completed.
KOMNINOU SHAFT
The following works have been completed:
- Masonry works, plastering works, door installation, industrial floor, painting works, installation of grids at street level, staircase balustrades, hatch
- Reinstatement at street level
AGHIA VARVARA STATION
The following works are in progress:
- Reinstatement at street level – Square level (fountain)
- Cladding of walls and columns (steel, glass, etc.)
- Installation of roller shutters
- Installation of handrails
- Other architectural finishes
MEGALOU ALEXANDROU SHAFT
Works have been completed.
KORYDALLOS STATION
The following works are in progress:
- Door installation
- Ceramic tiles installation
- Granite or marble installation
- Handrail installation
- Balustrades installation
NIKEA STATION
MAIN STATION
The following works are in progress:
- Final reinstatement (slab paving) at the station street level (– 0).
- Wall cladding with granite slabs at platform level (– 3).
- E/M works
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are put on hold:
- Door installation at E/M level
The following works are in progress:
- Preservation of the archaeological finds of the Project
- Opening of an exhibition area for the display of the project’s archeological finds at the building located at Pylon Street owned by the Directorate of Antiquities
ENTRANCE TO KORAI SQUARE AND ACCESS TUNNEL
The following works are in progress:
- Construction of a lift termination
DOUBLE TRACK TBM TUNNEL
Works have been completed.
TRIPLE TRACK NATM TUNNEL
DIRECTION UNIVERSITY OF PIRAEUS
The following works have been completed:
- Construction of permanent lining