DOUBLE TRACK ΝΑΤΜ START TUNNEL
Works have been completed.
KOMNINOU SHAFT
The following works have been completed:
- Masonry works, plastering works, door installation, industrial floor, painting works, installation of grids at street level, staircase balustrades, hatch
- Reinstatement at street level
AGHIA VARVARA STATION
The following works are in progress:
- Reinstatement at street level – Square level (granites, pathways, marble, fountain)
- Installation of false ceilings at the platform and concourse levels
- Cladding of walls and columns (steel, glass, etc.)
MEGALOU ALEXANDROU SHAFT
Works have been completed.
KORYDALLOS STATION
The following works are in progress:
- Cladding of walls and columns
- Installation of false ceiling
- Installation of ventilation grids
- Backfilling
NIKEA STATION
MAIN STATION
The following works are in progress:
- Final reinstatement at the station street level (– 0)
- Installation of horizontal false ceiling panels at the concourse (– 2) and platform (– 3) levels of the Station
- E/M works