KOMNINOU SHAFT
- Reinstatement works at street level
MEGALOU ALEXANDROU SHAFT
The following works are in progress:
- Archaeological works (painting works)
- Reinstatement works at street level
NIKEA STATION
MAIN STATION
The following works are in progress:
- Final reinstatement at the station street level (– 0)
MANIATIKA STATION
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works are in progress:
- Construction of walls and platform slabs
PIRAEUS STATION
STATION
The following works have been completed:
- Installation and preloading of struts for the temporary retaining of levels 1 , 2 , 3 and 4 and excavation works at levels 1, 2, 3, 4 and 5