AUGUST 2019

Α.            Tramway

  • Further to the completion of the works for the construction of the tramway the final tests – adjustments of the systems and devices controlling the operation of the Tramway system are still pending due to the suspension of the tramway vehicle trial runs on 19.07.2019 further to the blocking of a section of the tramway network at Omyrou Skylitsi Street due to an earthquake.
  • The E/M works at the new Substation 16 (Civil Works have been completed), as well as the upgrading of Substation 1 are pending.

Β.            OTHER WORKS (reference to extended work fronts)

  • Lambraki Bridge: Further to the completion of the concrete curing works, painting works have commenced and are in progress.
  • Further to the completion of the final tests, the underground waste bins have been delivered for use. The permanent electrification of some of them by the PCC is still pending.
  • Maintenance works and repair works for the reinstatement of minor deficiencies are being executed in all project structures.