DOUBLE TRACK NATM START TUNNEL
Works have been completed.
KOMNINOU SHAFT
The following works have been completed:
- Masonry, plastering, door installation, industrial floor, painting, grid installation at street level, staircase balustrades, hatch
- Street level reinstatement
AGHIA VARVARA STATION
The following works are in progress:
- Street – square level reinstatement
- Installation of handrails
- Other architectural finishes
MEGALOU ALEXANDROU SHAFT
Works have been completed.
The following works are still pending:
- Planting (street level)
TAXIARCHON SHAFT
The following works are in progress:
- Installation of doors
- Installation of ceramic tiles
- Installation of metal structures
KORYDALLOS STATION
The following works are in progress:
- Installation of doors
- Installation of granites or marbles
- Wall and Columns cladding
- Installation of ventilation grids
- Painting
NIKEA STATION
MAIN STATION
The following works are in progress:
- Final reinstatement (slab paving) at level -0 of the street
- Roof lining at various levels of the Station
- Wall cladding using granite slabs and metal cladding at various levels of the Station.
MANIATIKA STATION
OPEN CUT OF THE STATION
The following works are in progress:
- Permanent lining of E/M slab (level -3)
- Permanent lining of staircase S4
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor
- Waterproofing at street level
The following works are in progress:
- Painting at the E/M floor, at the ticketing and platform levels
- Plastering at platform level.