Kritis Shaft: The works for the construction of the permanent lining are in progress.
NOMARCHIA Station: The works for the construction of the terminations of shafts and their painting works have been completed. The works for the installation of granites at the platform and the construction of metal elements in the surrounding area are in progress.
KALAMARIA Station: Lining of public areas with granite slabs and wall cladding with fiber cement boards are in progress.
ARETSOU Station: Backfilling and surface reinstatement works are in progress.
NEA KRINI Station: The construction of metal elements, as well as the painting of the surrounding area are in progress. Moreover, the works for the installation of granites at the platform continue.
MIKRA Station (Station & Crossovers): The works related to the installation and setting of exterior escalators in the station have been completed. Wall cladding and painting works at the station are in progress. Moreover, the following works continue: installation of ceramic tiles, construction of metal elements and configuration of the surrounding area at the 1st Crossover.