VENIZELOU Station: The works for the dismantling of the metal bridge foundation base, a section of the southern diaphragm walls and the pile cap beans of the central piles are in progress.
AGHIA SOFIA Station: The works for the construction of the foundation slab are in progress.
PANEPISTIMIO Station: The works for the installation of the platform screen doors are in progress.
PAPAFI Station: The works for the installation of the platform screen doors are in progress.
FLEMING Station: The works for the installation of acoustic panels in the ventilation shafts are in progress.
VOULGARI Station: The works for the configuration of the surrounding area are in progress.
DEPOT:
Building Complex Ι: The works for the installation of the lighting system are in progress.
Building Complex ΙΙ: The works for the installation of gypsum boards and the installation of the rainwater network on the northern side are in progress. In addition, the works related to the installation of the signalling and traction power systems are in progress.
TBM tunnels: The works related to aluminum/thermal welding, the installation of sleepers and the construction of the floating slab – track 2, in a section of the project’s tunnels, are in progress.
In progress are the works for the installation of E/M installations in the following stations: NEW RAILWAY, SINTRIVANI/EXPO, PANEPISTIMIO, PAPAFI, EFKLIDIS, ANALIPSI (Station and Crossover), 25TH MARTIOU (Station and Crossover) and NEA ELVETIA.