DOUBLE TRACK NATM START TUNNEL
Works have been completed.
KOMNINOU SHAFT
The following works have been completed:
- Masonry, plastering, door installation, industrial floor, painting, grid installation at street level, staircase balustrades, hatch
- Street level reinstatement
AGHIA VARVARA STATION
The following works are in progress:
- Installation of lifts in the station
- Wall and columns cladding (metal, glass etc.)
- Installation of handrails
- Other architectural finishes
- Installation of station and other signs
- Installation of a fountain
- Planting and irrigation system
- Installation of false ceilings at the ticketing level.
MEGALOU ALEXANDROU SHAFT
Works have been completed.
The following works are still pending:
- Planting (street level)
TAXIARCHON SHAFT
The following works are in progress:
- Painting works
- Filling works and industrial floors
- Installation of doors
- Installation of ceramic tiles
- Installation of metal structures
KORYDALLOS STATION
The following works are in progress:
- Installation of doors
- Installation of granites or marbles
- Wall and Columns cladding
- Installation of false ceilings
- Installation of lift at street level
- Installation of handrails
- Installation of balustrades
PISSIDIAS SHAFT
The following works are in progress:
- Handrails – balustrades at the emergency staircase
- Final reinstatement at street level (removal – dismantling).
NIKEA STATION
MAIN STATION
The following works are in progress:
- Roof cladding using horizontal false ceiling panels at several levels of the Station
- Wall cladding using metal panels at level -3 of the platforms
- Final reinstatement of the surrounding area at street level (slab paving – minor structures’ concrete)
- Installation of metal shed at the central entrance of the Station
- Installation of metal structure to support the glass panels of the PSN lifts
- Preliminary works for the installation of fire rated glass panels at the public staircases, at level -3 of the platforms
- Preliminary works for the installation of aluminum glass panels in public areas, at level -1 of the E/M floor.
MANIATIKA STATION
OPEN CUT OF THE STATION
The following works have been completed:
- Permanent lining of foundation (level -4)
- Permanent lining of E/M slab (level -3)
- Permanent lining of staircase S4
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor
- Waterproofing at street level
The following works are in progress:
- Concreting of the east shaft termination
- Filing concrete underneath the platforms.