AGHIA VARVARA STATION
The following works are in progress:
- Installation of lifts in the station
- Wall and columns cladding (metal, glass etc.)
- Installation of handrails
- Other architectural finishes
- Installation of station and other signs
- Installation of a fountain
- Planting and irrigation system
- Installation of false ceilings at the ticketing level.
MEGALOU ALEXANDROU SHAFT
Works have been completed.
The following works are still pending:
- Planting (street level)
TAXIARCHON SHAFT
The following works are in progress:
- Painting works
- Installation of metal structures
- Configuration at street level
KORYDALLOS STATION
The following works are in progress:
- Wall and Columns cladding
- Installation of false ceilings
- Installation of lift at street level
- Installation of handrails
- Installation of balustrades
- Installation of Station entrances’ sheds
- Installation of lift at street level
- Configuration at street level (Eleftherias Square)
NIKEA STATION
MAIN STATION
The following works are in progress:
- Final reinstatement of the surrounding area
- Painting of parapet walls at terminating points, at street level (level 0)
- False ceilings
- Cladding of vertical elements using metal panels
MANIATIKA STATION
OPEN CUT OF THE STATION
The following works have been completed:
- Permanent lining of foundation (level -4)
- Permanent lining of E/M slab (level -3)
- Permanent lining of ticketing level slab (level -2)
- Permanent lining of staircase S4
The following works are in progress:
- Waterproofing of perimeter walls
- Permanent lining of perimeter walls, columns and intermediate slabs.
PIRAEUS STATION
STATION
The following works have been completed:
- Installation and prestressing of struts for temporary retaining at all levels.
The following works are in progress:
- Installation of reinforcement and concreting at roof bay #4.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor
- Waterproofing at street level
The following works are in progress:
- Filing concrete underneath the platforms
- Industrial floor paving at E/M floor
- Masonry walls at ticketing level
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.