Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

JANUARY 2020

 

AGHIA VARVARA STATION

The following works are in progress:

  • Installation of lifts in the station
  • Wall and columns cladding (metal, glass etc.)
  • Installation of handrails
  • Other architectural finishes
  • Installation of station and other signs
  • Installation of a fountain
  • Planting and irrigation system
  • Installation of false ceilings at the ticketing level.

MEGALOU ALEXANDROU SHAFT

Works have been completed.

 The following works are still pending:

  • Planting (street level)

TAXIARCHON SHAFT

The following works are in progress:

  • Painting works
  • Installation of metal structures
  • Configuration at street level

KORYDALLOS STATION

The following works are in progress:

  • Wall and Columns cladding
  • Installation of false ceilings
  • Installation of lift at street level
  • Installation of handrails
  • Installation of balustrades
  • Installation of Station entrances’ sheds
  • Installation of lift at street level
  • Configuration at street level (Eleftherias Square)

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Final reinstatement of the surrounding area
  • Painting of parapet walls at terminating points, at street level (level 0)
  • False ceilings
  • Cladding of vertical elements using metal panels

MANIATIKA STATION

OPEN CUT OF THE STATION

The following works have been completed:

  • Permanent lining of foundation (level -4)
  • Permanent lining of E/M slab (level -3)
  • Permanent lining of ticketing level slab (level -2)
  • Permanent lining of staircase S4

 The following works are in progress:

  • Waterproofing of perimeter walls
  • Permanent lining of perimeter walls, columns and intermediate slabs.

PIRAEUS STATION 

STATION

The following works have been completed:

  • Installation and prestressing of struts for temporary retaining at all levels.

The following works are in progress:

  • Installation of reinforcement and concreting at roof bay #4.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor
  • Waterproofing at street level

The following works are in progress:

  • Filing concrete underneath the platforms
  • Industrial floor paving at E/M floor
  • Masonry walls at ticketing level

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

 

WCAG