FEBRUARY 2020

 

AGHIA VARVARA STATION

The following works are in progress:

  • Installation of lifts in the station
  • Wall and columns cladding (metal, glass etc.)
  • Installation of balustrades
  • Installation of handrails
  • Other architectural finishes
  • Installation of a fountain
  • Planting and irrigation system
  • Installation of false ceilings at the ticketing level
  • Square reinstatement (Granites, Passageways, Marbles).

MEGALOU ALEXANDROU SHAFT

The following works are still pending:

  • Planting (street level).

TAXIARCHON SHAFT

The following works are in progress:

  • Painting works
  • Configuration at street level.

KORYDALLOS STATION

The following works are in progress:

  • Wall and Columns cladding
  • Installation of false ceilings
  • Installation of balustrades
  • Installation of roller shutters
  • Installation of irrigation system at street level
  • Installation of signage
  • Installation of Station entrances’ sheds
  • Installation of lift at street level
  • Configuration at street level (Eleftherias Square)

PISSIDIAS SHAFT

The following works are in progress:

  • Final reinstatement at street level

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Final reinstatement of the surrounding area
  • Painting of parapet walls of the superstructure
  • False ceilings
  • Floor paving using granite slabs
  • Wall cladding using metal panels
  • Station signage.

PIRAEUS STATION 

STATION

The following works have been completed:

  • Installation and prestressing of struts for temporary retaining at all levels
  • Installation of waterproofing and concreting of the foundation (bay 4).

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor.

The following works are in progress:

  • Masonry walls at ticketing level
  • Waterproofing at street level
  • Backfilling – compaction related works
  • Cleaning works

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

 

 