AGHIA VARVARA STATION
The following works are in progress:
- Installation of lifts in the station
- Wall and columns cladding (metal, glass etc.)
- Installation of balustrades
- Installation of handrails
- Other architectural finishes
- Installation of a fountain
- Planting and irrigation system
- Installation of false ceilings at the ticketing level
- Square reinstatement (Granites, Passageways, Marbles).
MEGALOU ALEXANDROU SHAFT
The following works are still pending:
- Planting (street level).
TAXIARCHON SHAFT
The following works are in progress:
- Painting works
- Configuration at street level.
KORYDALLOS STATION
The following works are in progress:
- Wall and Columns cladding
- Installation of false ceilings
- Installation of balustrades
- Installation of roller shutters
- Installation of irrigation system at street level
- Installation of signage
- Installation of Station entrances’ sheds
- Installation of lift at street level
- Configuration at street level (Eleftherias Square)
PISSIDIAS SHAFT
The following works are in progress:
- Final reinstatement at street level
NIKEA STATION
MAIN STATION
The following works are in progress:
- Final reinstatement of the surrounding area
- Painting of parapet walls of the superstructure
- False ceilings
- Floor paving using granite slabs
- Wall cladding using metal panels
- Station signage.
PIRAEUS STATION
STATION
The following works have been completed:
- Installation and prestressing of struts for temporary retaining at all levels
- Installation of waterproofing and concreting of the foundation (bay 4).
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor.
The following works are in progress:
- Masonry walls at ticketing level
- Waterproofing at street level
- Backfilling – compaction related works
- Cleaning works
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.