NEW RAILWAY STATION: Works for the reinstatement of the indoor lift and works for the preparation of the tunnel filling concrete are in progress.
DIMOKRATIAS Station (Station & Crossover): In the framework of the 30th Traffic Reinstatement Plan, works for the construction of the central island at Monastiriou Street have been completed.
VENIZELOU Station: Works for the construction of the station roof slab at the south section have been completed.
AGHIA SOFIA Station: Platform construction works have been completed. The construction of a ventilation shaft/emergency exit and the construction of a north and south access are in progress.
ANALIPSI Station (Station & Crossover): Works for the construction of the tunnel track bed are in progress.
DEPOT:
Building Complex Ι: The installation of balustrades is in progress.
Building Complex ΙΙ: The works for the construction of the outdoor false ceiling are in progress.
ΤΒΜ Tunnels: Trackwork construction works at a section of the project tunnels are in progress.
E/M works at DIMOKRATIAS, SINTRIVANI/EXPO, PANEPISTIMIO, EFKLIDIS, 25 MARTIOU (Station and Crossover) and NEA ELVETIA Stations are in progress.